OPTIMAL PRODUCTION WITH UNCERTAIN INTERRUPTIONS IN THE SUPPLY OF ELECTRICITY - ESTIMATION OF ELECTRICITY OUTAGE COSTS

被引:29
作者
TISHLER, A
机构
[1] Tel-Aviv University, Tel Aviv
关键词
D O I
10.1016/0014-2921(93)90134-V
中图分类号
F [经济];
学科分类号
02 ;
摘要
In this paper we develop a model to measure expected electricity outage costs in the industrial and commercial sectors. Four sources contribute to the costs of outage in these sectors: foregone profits (output), possible reduction in productivity due to the outage, damage to materials, and payments to labor during the outage. The beginning and duration of the electricity outage are random variables with known distribution functions. Thus, the business customer maximizes his expected profits, taking into account his ability, or lack of ability, to respond to the random electricity outage. The model is applied, assuming a quadratic production function, to eleven industrial branches in Israel. The estimates indicate a large variation in customer preferences for reliability.
引用
收藏
页码:1259 / 1274
页数:16
相关论文
共 32 条
[1]  
ANDERSSON R, 1986, ENERG ECON, P139
[2]   CHOICE OF FUNCTIONAL FORMS [J].
APPELBAUM, E .
INTERNATIONAL ECONOMIC REVIEW, 1979, 20 (02) :449-458
[3]   A SIMPLE METHOD FOR EVALUATING THE MARGINAL COST OF UNSUPPLIED ELECTRICITY [J].
BENTAL, B ;
RAVID, SA .
BELL JOURNAL OF ECONOMICS, 1982, 13 (01) :249-253
[4]   PARAMETRIC PRODUCTIVITY-MEASUREMENT AND CHOICE AMONG FLEXIBLE FUNCTIONAL FORMS [J].
BERNDT, ER ;
KHALED, MS .
JOURNAL OF POLITICAL ECONOMY, 1979, 87 (06) :1220-1245
[5]  
Caves D. W., 1990, B ECON RES, V42, P79, DOI DOI 10.1111/J.1467-8586.1990.TB00294.X
[6]  
CAVES DW, 1988, ESTIMATING OUTAGE CO
[7]  
CHAO HP, 1983, BELL J ECON, V14, P179
[8]  
CHAO HP, 1989, ENERGY, V9, P77
[9]  
COATE R, 1989, J REGULATORY EC, V1, P305
[10]  
CREW MA, 1978, AM ECON REV, V68, P31