EFFECT OF INEQUALITY OF INTERSTAGE BUFFER CAPACITIES AND OPERATION TIME VARIABILITY ON THE EFFICIENCY OF PRODUCTION LINE SYSTEMS

被引:31
作者
ELRAYAH, TE
机构
[1] Department of Business Administration, University of Khartoum, Khartoum
关键词
D O I
10.1080/00207547908919596
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
It has now been generally established that the output rate of balanced production lines having variable operation times can be improved by deliberately unbalancing the line through assigning proportionately lower operation times to the middle station(s). Nevertheless, a production line may be balanced in terms of mean operation times at the respective stations yet unbalanced in the sense that the interstage buffer capacity allocation or the operation time variability are not equal for all stations. This paper attempts to study the effect that the latter types of imbalance have on the output rate and average number of work units in the system for some production line situations. Computer simulation experimentation results confirm that inequality of variability of operation times have the same general effect on output rate as inequality of operation times but little effect on the number of units in the system. Inequality of interstage buffers, on the other hand, affects the average number of units in the system but has little effect on the output rate. © 1979, Taylor & Francis Group, LLC.
引用
收藏
页码:77 / 89
页数:13
相关论文
共 4 条
[1]  
Bzohhoffer R.E., Ditnnett C.W., Sobel M., A two sample multiple decision procedure for ranking means of normal populations with a common unknown variance, Biometrica, 41, (1954)
[2]  
Dunnett C.W., A multiple comparison. Procedure for comparing several treatments with a control, J. Am. Statist. Assoc, 50, (1956)
[3]  
Erayah T.E., Computer Simulation Studies into the Efficiency of Various Production System Designs, (1973)
[4]  
Tctkey J.W., The Problem of Multiple Comparisons, (1953)