BREACH OF A NATURALLY EMBANKED DAM ON YALONG RIVER

被引:20
作者
CHEN, YJ
ZHOU, F
FENG, Y
XIA, YC
机构
[1] HAIHE RIVER CONSERVANCY COMMISS,TIANJIN 300170,PEOPLES R CHINA
[2] TIANJIN PROSPECTING & DESIGN INST,SCI RES DEPT,TIANJIN 300222,PEOPLES R CHINA
关键词
LANDSLIDE DAM; COHESIONLESS MATERIAL; OVERTOPPING; BREACH; FLOOD; HYDROGRAPH; FAILURE PROCESS;
D O I
10.1139/l92-092
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
A huge slide involving 68 x 10(6) m3 of soils occurred along the right bank of Yalong River in Sichuan Province, China. The sliding materials blocked the river and formed a dam-like structure having a height of 175 m and creating a reservoir with a capacity of approximately 680 x 10(6) m3. The dam breach which was caused by overtopping lasted 13 h and resulted in an estimated maximum flood discharge of 53 000 m3/s. Based on the hydrograph created by measuring the flows downstream of the dam, the process of dam breach was roughly estimated.
引用
收藏
页码:811 / 818
页数:8
相关论文
共 11 条
[2]  
Johnson F.A., 1976, WATER POWER DAM CONS, V28, P43
[3]  
KRAMER RW, 1985, 15TH T INT C LARG DA, V5, P531
[4]  
Lee K. L., 1975, LANDSLIDE APRIL 25 1
[5]   BREACHING CHARACTERISTICS OF DAM FAILURES [J].
MACDONALD, TC ;
LANGRIDGEMONOPOLIS, J .
JOURNAL OF HYDRAULIC ENGINEERING-ASCE, 1984, 110 (05) :567-586
[6]  
MIDDLEBROOKS TA, 1952, CIVIL ENG, V22, P118
[7]  
ODENDAAL WA, 1979, 13TH T INT C LARG DA, V2, P141
[8]  
PONCE VM, 1981, ASCE J HYDRAULIC ENG, V107, P829
[9]  
SIMMLER H, 1982, 14TH T INT C LARG DA, V1, P427
[10]  
Singh V.P., 1988, ASCE J HYDRAUL ENG, V114, P21