客观地评述了关键链方法的优缺点.首先,简要阐述了关键链与关键路径法/计划评审技术及资源约束型项目调度问题的异同点;然后,从关键链调度优化模型、缓冲机制和关键链的应用3方面梳理了已有的研究成果,相应地,从两个方面总结出目前关键链方法中的欠缺;最后,从多目标优化、动态关键链、与鲁棒性结合和与其他理论融合4个角度指出了关键链方法将来的研究趋势.评述工作将会对关键链的理论研究和实践应用提供一些思维启发.
引用
收藏
页码:1281 / 1287
页数:7
相关论文
共 33 条
[1]   A process framework for theoretically grounded prescriptive research in the project management field [J].
Ahlemann, Frederik ;
El Arbi, Fedi ;
Kaiser, Michael G. ;
Heck, Axel .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2013, 31 (01) :43-56
[2]   Buffer sizing approach with dependence assumption between activities in critical chain scheduling [J].
Bie, Li ;
Cui, Nanfang ;
Zhang, Xiaoming .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2012, 50 (24) :7343-7356
[3]  
The Review of Project Management Based on the Theory of Constraints and Critical Chain.[J].Zhang Zhao;Guo Bing;Chen Gui Xiang;Song Jiu Le.Applied Mechanics and Materials.2012, 174
[4]  
A Critical Chain Project Scheduling Problem with Multi-Mode.[J].Peng Wu Liang;Jiao Q.J..Materials Science Forum.2012, 697
[5]  
Critical chain and risk analysis applied to high-risk industry maintenance: A case study.[J].M. Bevilacqua;F.E. Ciarapica;G. Giacchetta.International Journal of Project Management.2008, 4
[6]  
Fuzzy critical chain method for project scheduling under resource constraints and uncertainty.[J].Luong Duc Long;Ario Ohsato.International Journal of Project Management.2007, 6
[7]   Introduction to the special issue: project scheduling under uncertainty [J].
Demeulemeester, Erik ;
Herroelen, Willy .
JOURNAL OF SCHEDULING, 2007, 10 (03) :151-152
[8]  
The evolution of a management philosophy: The theory of constraints.[J].Kevin J. Watson;John H. Blackstone;Stanley C. Gardiner.Journal of Operations Management.2006, 2
[9]  
Critical Chain: A New Project Management Paradigm or Old Wine in New Bottles?.[J].Thomas G. Lechler;Boaz Ronen;Edward A. Stohr.Engineering Management Journal.2005, 4
[10]  
A new heuristic for resource-constrained project scheduling in stochastic networks using critical chain concept.[J].M. Rabbani;S.M.T. Fatemi Ghomi;F. Jolai;N.S. Lahiji.European Journal of Operational Research.2005, 2