Modelling setup times, process batches and transfer batches using activity network logic

被引:15
作者
Demeulemeester, EL [1 ]
Herroelen, WS [1 ]
机构
[1] KATHOLIEKE UNIV LEUVEN,DEPT APPL ECON,B-3000 LOUVAIN,BELGIUM
关键词
project management; generalized resource-constrained project scheduling; production planning; generalized job shop scheduling;
D O I
10.1016/0377-2217(94)00249-5
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
The objective of this paper is to demonstrate how modelling ideas and solution procedures, borrowed from the field of generalized resource-constrained project scheduling, can be used to formulate and solve several types of production scheduling problems involving sequence-independent setup times as well as process and transfer batches. The computational results provide useful insight in the trade-offs that do exist between the computational effort required and the size of the process and transfer batches used.
引用
收藏
页码:355 / 365
页数:11
相关论文
共 16 条
[1]  
Bartusch M., 1988, Annals of Operations Research, V16, P201
[2]   COMPARISON OF HEURISTIC AND OPTIMUM SOLUTIONS IN RESOURCE-CONSTRAINED PROJECT SCHEDULING [J].
DAVIS, EW ;
PATTERSON, JH .
MANAGEMENT SCIENCE SERIES B-APPLICATION, 1975, 21 (08) :944-955
[3]   A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM [J].
DEMEULEMEESTER, E ;
HERROELEN, W .
MANAGEMENT SCIENCE, 1992, 38 (12) :1803-1818
[4]  
Demeulemeester E., 1992, THESIS KATHOLIEKE U
[5]  
DEMEULEMEESTER E, 1992, 9206 KATH U LEUV DEP
[6]   AN EVALUATION OF MICROCOMPUTER-BASED SOFTWARE PACKAGES FOR PROJECT-MANAGEMENT [J].
DEWIT, J ;
HERROELEN, W .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1990, 49 (01) :102-139
[7]  
Goldratt E.M., 1990, HAYSTACK SYNDROME
[8]  
Goldratt E.M., 1986, RACE, V1st
[9]  
GOLDRATT EM, 1986, GOAL
[10]  
GOLDRATT EM, 1990, THEORY CALLED THEORY