Water circulation control during once-through boiler start-up

被引:10
作者
Eitelberg, E
Boje, E
机构
[1] NOY Business, ZA-4001 Durban, South Africa
[2] Univ Natal, ZA-4041 Durban, South Africa
关键词
once-through boiler start-up; level control; circulating water flow control; limit cycling;
D O I
10.1016/S0967-0661(03)00153-9
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
A loop-by-loop approach is used to analyse multivariable water flow and collecting vessel-level control problems during Benson(R) type boiler start-up. It is shown that the circulation loop must be tuned so that its bandwidth is less than the feed water loop bandwidth. (C) 2003 Published by Elsevier Ltd.
引用
收藏
页码:677 / 685
页数:9
相关论文
共 4 条
[1]  
[Anonymous], 1999, LOAD SHARING CONTROL
[2]  
Eitelberg E., 1991, OPTIMAL ESTIMATION E
[3]  
Lausterer G. K., 1980, 6 IFAC IFIP C DIG CO, P411
[4]  
Maffezzoni C., 1989, Journal A, V30, P7