An ant-colony optimization algorithm for minimizing the completion-time variance of jobs in flowshops

被引:70
作者
Gajpal, Y [1 ]
Rajendran, C [1 ]
机构
[1] Indian Inst Technol, Dept Management Studies, Madras 600036, Tamil Nadu, India
关键词
scheduling; flowshop; completion-time variance; ant-colony algorithm;
D O I
10.1016/j.ijpe.2005.01.003
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The problem of scheduling in permutation flowshops with the objective of minimizing the completion-time variance of jobs is considered and solved by making use of ant-colony optimization (ACO) algorithms. ACO is an algorithmic approach, inspired by the foraging behavior of real ants, which can be applied to solve combinatorial optimization problems. A new ant-colony algorithm (NACO) has been developed in this paper to solve the flowshop, scheduling problem. The objective is to minimize the completion-time variance of jobs. Two existing ant-colony algorithms and the proposed ant-colony algorithm have been compared with an existing heuristic for scheduling with the objective of minimizing the completion-time variance of jobs. It is found that the proposed ant-colony algorithm gives promising and better results, on an average, as compared to those solutions given by the existing ant-colony algorithms and the existing heuristic for the permutation flowshop scheduling problem under study. (c) 2005 Elsevier B.V. All rights reserved.
引用
收藏
页码:259 / 272
页数:14
相关论文
共 32 条
[1]   New heuristics to minimize total completion time in m-machine flowshops [J].
Allahverdi, A ;
Aldowaisan, T .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2002, 77 (01) :71-83
[2]   MINIMIZING MEAN SQUARED DEVIATION OF COMPLETION TIMES ABOUT A COMMON DUE DATE [J].
BAGCHI, U ;
SULLIVAN, RS ;
CHANG, YL .
MANAGEMENT SCIENCE, 1987, 33 (07) :894-906
[3]   A tabu search approach for the flow shop scheduling problem [J].
Ben-Daya, M ;
Al-Fawzan, M .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1998, 109 (01) :88-95
[4]  
CAMPBELL HG, 1970, MANAGE SCI B-APPL, V16, pB630
[5]   The development of gradual-priority weighting approach for the multi-objective flowshop scheduling problem [J].
Chang, PC ;
Hsieh, JC ;
Lin, SG .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2002, 79 (03) :171-183
[6]   A branch and bound algorithm to minimize the total flow time for m-machine permutation flowshop problems [J].
Chung, CS ;
Flynn, J ;
Kirca, O .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2002, 79 (03) :185-196
[7]   Ant system: Optimization by a colony of cooperating agents [J].
Dorigo, M ;
Maniezzo, V ;
Colorni, A .
IEEE TRANSACTIONS ON SYSTEMS MAN AND CYBERNETICS PART B-CYBERNETICS, 1996, 26 (01) :29-41
[8]   MINIMIZING WAITING TIME VARIANCE IN SINGLE MACHINE PROBLEM [J].
EILON, S ;
CHOWDHURY, IG .
MANAGEMENT SCIENCE, 1977, 23 (06) :567-575
[9]   4 SIMPLE HEURISTICS FOR SCHEDULING A FLOW-SHOP [J].
GELDERS, LF ;
SAMBANDAM, N .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1978, 16 (03) :221-231
[10]   Flow shop scheduling algorithms for minimizing the completion time variance and the sum of squares of completion time deviations from a common due date [J].
Gowrishankar, K ;
Rajendran, C ;
Srinivasan, G .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2001, 132 (03) :643-665