Development of reliability targets for planning transmission facilities using probabilistic techniques - A utility approach

被引:9
作者
Agarwal, SK [1 ]
Torre, WV [1 ]
机构
[1] SAN DIEGO GAS & ELECT CO,SAN DIEGO,CA 92112
关键词
Cost effectiveness - Database systems - Electric substations - Outages - Probability - Strategic planning;
D O I
10.1109/59.589658
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
This paper documents a new probabilistic approach to transmission planning outage by taking advantage of the outage database and new computer programs which are available. This approach provides reliability indices which will be used to evaluate expected system performance and provides a quantifiable method to evaluate overall transmission system performance. It also provides a consistent and quantifiable method to rank transmission projects and helps to provide a measure of impact on reliability for each and every project addition.
引用
收藏
页码:704 / 709
页数:6
相关论文
共 10 条
[1]  
Allan RN, 1991, APPL RELIABILITY ASS
[2]  
BESHIR MJ, 1994, THESIS U SO CALIFORN
[3]  
Billinton R., 1988, RELIABILITY ASSESSME, DOI DOI 10.1007/978-1-4613-1689-3
[4]  
Billinton R, 1991, IEE P C, V138
[5]  
BILLINTON R, 1986, 86SP141 CAN EL ASS, V25
[6]  
*CAL EN COMM, 1989, CAL UT RES MARG PLAN
[7]  
NEUDORF EG, 1995 IEEE WINT POW M
[8]  
RINGLEE RJ, 1994, IEEE T POWER SYST, V9, P181, DOI 10.1109/59.317611
[9]  
VOJDANI AF, 1995 IEEE SUMM POW M
[10]  
1995, TRANSMISSION RELIABI, V2