Selection priority of process areas based on CMMI continuous representation

被引:26
作者
Huang, SJ [1 ]
Han, WM [1 ]
机构
[1] Natl Taiwan Univ Sci & Technol, Dept Informat Management, Taipei 106, Taiwan
关键词
capability maturity model integration; software process improvement; critical success process areas; project management; information system characteristics;
D O I
10.1016/j.im.2005.08.003
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
An essential decision that must be made by software organizations that adopt the continuous representation of the capability maturity model integration (CMMI) for software process improvement concerns a Suitable path that best meets their business objectives and mitigates the organization's risk. However, the CMMI models released by the Software Engineering Institute do not give their adopters any guidance on how to make such a decision. Thus, managers often make subjective selections of the areas in which to implement process improvement. Our study presents a decision support model that assists managers in determining the priorities of the CMMI process areas based on the characteristics of the is being developed. The proposed model was validated by using the ISBSG repository, and an example is presented to demonstrate the application of the model. Given the fact that hardly any research has yet been clone on how to select the CMMI process areas to initialize process improvement, this study provides a starting point for the community in considering this important issue. (c) 2005 Elsevier B.V. All rights reserved.
引用
收藏
页码:297 / 307
页数:11
相关论文
共 27 条
[1]  
[Anonymous], 1992, LECT NOTES ECON M, DOI DOI 10.1007/978-3-642-46768-4_5
[2]  
[Anonymous], 1993, CAPABILITY MATURITY
[3]  
BRODMAN JG, 1995, RETURN INVESTMENT SO
[4]   Extensions of the TOPSIS for group decision-making under fuzzy environment [J].
Chen, CT .
FUZZY SETS AND SYSTEMS, 2000, 114 (01) :1-9
[5]  
*CMMI PROD TEAM, 2002, CMUSEI2002TR011
[6]  
*CMMI PROD TEAM, 2002, CMUSEI2002TR012
[7]  
Cooper J., 2002, CMU/SEI-2002-TR-010
[8]  
Curtis B., 1995, CMUSEI95MM02
[9]   Combining numerical and linguistic information in group decision making [J].
Delgado, M ;
Herrera, F ;
Herrera-Viedma, E ;
Martinez, L .
INFORMATION SCIENCES, 1998, 107 (1-4) :177-194
[10]   How software process improvement helped Motorola [J].
Diaz, M ;
Sligo, J .
IEEE SOFTWARE, 1997, 14 (05) :75-81