V-shape property for job sequences that minimize the expected completion time variance

被引:15
作者
Cai, X
机构
[1] Dept. of Syst. Eng. and Eng. Mgmt., Chinese University of Hong Kong, Shatin, NT
关键词
stochastic scheduling; completion time variance; V-shape property;
D O I
10.1016/0377-2217(95)00097-6
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
We consider the problem of sequencing n jobs with random processing times on a single machine so as to minimize the expected variance of job completion times. Our main result is a new sufficient condition for an optimal sequence to be V-shaped in terms of the mean processing times when n greater than or equal to 3. We show that this condition is satisfied by a wide variety of problem instances, including those in which the processing times follow different patterns of distributions. This result relaxes a condition proposed before.
引用
收藏
页码:118 / 123
页数:6
相关论文
共 14 条
[1]   SEQUENCING WITH EARLINESS AND TARDINESS PENALTIES - A REVIEW [J].
BAKER, KR ;
SCUDDER, GD .
OPERATIONS RESEARCH, 1990, 38 (01) :22-36
[2]   MINIMIZATION OF AGREEABLY WEIGHTED VARIANCE IN SINGLE-MACHINE SYSTEMS [J].
CAI, X .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1995, 85 (03) :576-592
[3]   ON THE MINIMIZATION OF COMPLETION-TIME VARIANCE WITH A BICRITERIA EXTENSION [J].
DE, P ;
GHOSH, JB ;
WELLS, CE .
OPERATIONS RESEARCH, 1992, 40 (06) :1148-1155
[4]   MINIMIZING WAITING TIME VARIANCE IN SINGLE MACHINE PROBLEM [J].
EILON, S ;
CHOWDHURY, IG .
MANAGEMENT SCIENCE, 1977, 23 (06) :567-575
[5]  
GUPTA MC, 1990, J OPER RES SOC, V41, P767
[6]   EARLINESS-TARDINESS SCHEDULING PROBLEMS .2. DEVIATION OF COMPLETION TIMES ABOUT A RESTRICTIVE COMMON DUE DATE [J].
HALL, NG ;
KUBIAK, W ;
SETHI, SP .
OPERATIONS RESEARCH, 1991, 39 (05) :847-856
[7]   EARLINESS-TARDINESS SCHEDULING PROBLEMS .1. WEIGHTED DEVIATION OF COMPLETION TIMES ABOUT A COMMON DUE DATE [J].
HALL, NG ;
POSNER, ME .
OPERATIONS RESEARCH, 1991, 39 (05) :836-846
[8]  
Hardy G.H., 1952, Inequalities
[9]   MINIMIZING VARIATION OF FLOW TIME IN SINGLE-MACHINE SYSTEMS [J].
KANET, JJ .
MANAGEMENT SCIENCE, 1981, 27 (12) :1453-1459
[10]   MINIMIZING WEIGHTED NUMBER OF TARDY JOBS AND WEIGHTED EARLINESS TARDINESS PENALTIES ABOUT A COMMON DUE DATE [J].
LEE, CY ;
DANUSAPUTRO, SL ;
LIN, CS .
COMPUTERS & OPERATIONS RESEARCH, 1991, 18 (04) :379-389