Integrated generation and transmission maintenance scheduling with network constraints

被引:109
作者
Marwali, MKC [1 ]
Shahidehpour, SM [1 ]
机构
[1] IIT, Dept Elect & Comp Engn, Chicago, IL 60616 USA
关键词
generation maintenance scheduling; transmission maintenance scheduling; benders decomposition;
D O I
10.1109/59.709100
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
Most unit maintenance scheduling packages consider preventive maintenance schedule of generating units over a one or two year operational planning period in order to minimize the total operating cost while satisfying system energy requirements and maintenance constraints. In a global maintenance scheduling problem, we propose to consider transmission line maintenance scheduling and line capacity limits along with generation and line outages. The inclusion of transmission and network constraints in generating unit maintenance will increase the complexity of the problem, so we propose to decompose the global generator/transmission scheduling problem into a master problem and sub-problems using Benders decomposition. In the first stage, a master problem is solved to determine a solution for maintenance schedule decision variables. In the second stage, sub-problems are solved to minimize operating costs while satisfying the network constraints. Benders cuts based on the solution of the sub-problem are introduced to the master problem for improving the existing solution. The iterative procedure continues until an optimal or near optimal solution is found.
引用
收藏
页码:1063 / 1068
页数:6
相关论文
共 14 条
[1]  
[Anonymous], 1979, IEEE T POWER AP SYST, V98, P2047, DOI 10.1109/TPAS.1979.319398
[3]   OPTIMAL GENERATING-UNIT MAINTENANCE SCHEDULING FOR MULTIAREA SYSTEM WITH NETWORK CONSTRAINTS [J].
CHEN, L ;
TOYODA, J .
IEEE TRANSACTIONS ON POWER SYSTEMS, 1991, 6 (03) :1168-1174
[4]   TECHNIQUE FOR AUTOMATED SCHEDULING OF MAINTENANCE OF GENERATING FACILITIES [J].
CHRISTIAANSE, WR ;
PALMER, AH .
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1972, PA91 (01) :137-+
[5]   A NEW APPROACH TO RELIABILITY EVALUATION OF INTERCONNECTED POWER-SYSTEMS INCLUDING PLANNED OUTAGES AND FREQUENCY CALCULATIONS [J].
DENG, Z ;
SINGH, CN ;
SHETTY, HVK .
IEEE TRANSACTIONS ON POWER SYSTEMS, 1992, 7 (02) :734-743
[6]   OPTIMAL GENERATOR MAINTENANCE SCHEDULING USING INTEGER PROGRAMMING [J].
DOPAZO, JF ;
MERRILL, HM .
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1975, 94 (05) :1537-1545
[7]   EXPERIMENTAL-METHOD OF DETERMINATION OF OPTIMAL MAINTENANCE SCHEDULES IN POWER-SYSTEMS USING BRANCH-AND-BOUND TECHNIQUE [J].
EGAN, GT ;
DILLON, TS ;
MORSZTYN, K .
IEEE TRANSACTIONS ON SYSTEMS MAN AND CYBERNETICS, 1976, 6 (08) :538-547
[8]   ADJUSTING MAINTENANCE SCHEDULES TO LEVELIZE RISK [J].
GARVER, LL .
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1972, 91 (05) :2057-&
[9]   A METHOD FOR PLANNING ECONOMIC UNIT COMMITMENT AND MAINTENANCE OF THERMAL POWER SYSTEMS [J].
HARA, K ;
KIMURA, M ;
HONDA, N .
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1966, PA85 (05) :427-&
[10]  
Lasdon LeonS., 2013, OPTIMIZATION THEORY