Scheduling with co-evolving resource availability profiles

被引:6
作者
Chua, DKH
Chan, WT
Kannan, G
机构
[1] Dept. of Civil Engrg, National University of Singapore
来源
CIVIL ENGINEERING SYSTEMS | 1996年 / 13卷 / 04期
关键词
project management; resource scheduling; resource allocation; resource utilization; resource hiring; genetic algorithm (GA);
D O I
10.1080/02630259608970206
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Existing resource allocation models schedule activities by balancing resource requirement with resource availability using the resource available profile as a constraint to guide the scheduling process. The given resource available profile, however, may not be the best configuration for the project. Consequently, the resource available profile may have to be modified to produce improved resource utilization. With each modification the activities have to be rescheduled to meet resource availability constraints. A model is presented herein which is able to generate activity schedules that is optimal with respect to the resource available profile that is configured interactively with the schedule for minimum resource idling. The entire project is subdivided into separate resource contracts. The model then employs genetic algorithm (GA) to determine the start times of the activities and simultaneously self-adjust the resource hiring levels and end-dates for each contract in order to minimize the objective function. Results show that the model can provide schedules and corresponding resource available profiles that yield considerable savings in idle resources even in multi-resource problems.
引用
收藏
页码:311 / 329
页数:19
相关论文
共 12 条
[1]   RISK-EVALUATION IN RESOURCE-ALLOCATION [J].
AHUJA, HN ;
ARUNACHALAM, V .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1984, 110 (03) :324-336
[2]  
Baker J. E., 1985, Proceedings of the International Conference on Genetic Algorithms and their Applications, P101
[3]  
CHAN WT, 1996, J CONSTRUCTION ENG M
[4]   RESOURCE LEVELING IN CONSTRUCTION BY OPTIMIZATION [J].
EASA, SM .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02) :302-316
[5]  
Goldberg DE, 1989, GENETIC ALGORITHMS S
[6]  
GREFENSTETTE JJ, 1983, USERS GUIDE GENESIS
[7]   RESOURCE-MANAGEMENT IN CONSTRUCTION [J].
KARAA, FA ;
NASR, AY .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03) :346-357
[8]  
LEE I, 1993, PROCEEDINGS OF THE FIFTH INTERNATIONAL CONFERENCE ON GENETIC ALGORITHMS, P383
[9]  
Moder J.J., 1983, Project Management with CPM, PERT and Precedence Diagramming
[10]   TIME-CONSTRAINED RESOURCE LEVELING [J].
SEIBERT, JE ;
EVANS, GW .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (03) :503-520