Scheduling of parts and robot activities in a two machine robotic cell

被引:46
作者
Aneja, YP [1 ]
Kamoun, H
机构
[1] Univ Windsor, Fac Business Adm, Windsor, ON N9B 3P4, Canada
[2] Fac Sci Econ & Gest, Sfax, Tunisia
关键词
manufacturing; robotic cell; deterministic scheduling; traveling salesman problem; algorithm;
D O I
10.1016/S0305-0548(98)00063-X
中图分类号
TP39 [计算机的应用];
学科分类号
081203 [计算机应用技术]; 0835 [软件工程];
摘要
We consider a scheduling problem arising in a two machine flexible robotic cell that repetitively produces parts of different types. We consider the two decisions that need to be made simultaneously: finding the robot move cycle, and finding the input part sequence. The objective is to maximize the throughput rate of the cell subject to the condition that parts are to be produced in proportion of their demand. The problem can be formulated as a special kind of traveling salesman problem. An O(n(4)) time algorithm which solves this problem optimally has been provided in Hall et al. (1997). In this paper, we extend their work and provide an algorithm of complexity O(n log n). (C) 1999 Elsevier Science Ltd. All rights reserved.
引用
收藏
页码:297 / 312
页数:16
相关论文
共 7 条
[1]
Ahuja RK., 1993, NETWORK FLOWS THEORY
[2]
SEQUENCING 1 STATE-VARIABLE MACHINE - SOLVABLE CASE OF TRAVELING SALESMAN PROBLEM [J].
GILMORE, PC ;
GOMORY, RE .
OPERATIONS RESEARCH, 1964, 12 (05) :655-&
[3]
Scheduling in robotic cells: Classification, two and three machine cells [J].
Hall, NG ;
Kamoun, H ;
Sriskandarajah, C .
OPERATIONS RESEARCH, 1997, 45 (03) :421-439
[4]
HALL NG, 1994, SCHEDULING ROBOTIC C
[5]
KAMOUN H, 1994, SCHEDULING ROBOTIC C
[6]
LAWLER EL, TRAVELING SALESMAN P
[7]
Sethi S. P., 1992, International Journal of Flexible Manufacturing Systems, V4, P331, DOI 10.1007/BF01324886