Line outage ranking for voltage limit violations with corrective rescheduling avoiding masking

被引:6
作者
Arya, LD [1 ]
Choube, SC [1 ]
Kothari, DP [1 ]
机构
[1] Shri GS Inst Technol & Sci, Dept Elect Engn, Indore 452003, Madhya Pradesh, India
关键词
line outage ranking; voltage limit violations; post-outage correctability;
D O I
10.1016/S0142-0615(00)00087-9
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
This paper describes a technique for ranking line outages causing voltage limit violations taking into account the post-outage correctability of the network during contingency selection process. Due to the choice of large even powered of performance index (PI): (i) masking is avoided; and (ii) complete potential of correctability, of power network is utilised. Fletcher and Reeves conjugate gradient method is used for optimisation. Use of newly derived compensated voltage shift factor has been made. To restrict the reactive power limit violations at generation buses, use of newly derived reactive power compensated shift factor has been made. Control corrections have been optimised for each line outage in the same base case pre-outage condition itself. This allows the use of same set of pre-outage sensitivity coefficients and line outage distribution factors. It is to be stressed here that the control corrections have been obtained for each line outage in pre-contingency condition mainly for computational convenience. But actually these corrections are applied in respective post-outage conditions. The algorithm is tested on IEEE 25-bus, 30-bus and 91-bus test systems. (C) 2001 Elsevier Science Ltd. All rights reserved.
引用
收藏
页码:837 / 846
页数:10