A workload balancing model for determining set-up time and batch size reductions in GT flow line workcells

被引:8
作者
Gung, RR
Steudel, HJ
机构
[1] IBM Corp, Mfg Ind Solut Lab, Supply Chain Optimizat, Hawthorne, NY 10532 USA
[2] Univ Wisconsin, Dept Ind Engn, Madison, WI 53706 USA
关键词
Benchmarking - Cellular manufacturing - Computer simulation - Constraint theory - Group technology - Heuristic methods - Inventory control - Mathematical models - Process control - Scheduling - Strategic planning - System stability;
D O I
10.1080/002075499191517
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Set-up time and batch size reductions-cornerstones of Quick Response Manufacturing (QRM)-are often viewed as pathways leading to lower work-in-process (WIP) inventory levels and reduced manufacturing lead times. However, set-up time and batch size reductions may not always yield such improvements. Increased workload due to the additional set-ups can lead to a violation of the system's capacity constraints and cause system instability, which results in increased manufacturing lead times and WIP inventory levels. A workload balancing model in conjunction with a heuristic model is presented to determine the required set-up time reduction schemes for different levels of batch size reduction. The model is based on the Theory of Constraints to balance the flow line and limit the workload of each workstation such that each workstation meets the reserved capacity constraint. It is shown that a reduction plan determined by the workload balancing model will maintain the cell's system stability and improve its performance. Incorporating the workload balancing and simulation models, a general approach for selecting the most appropriate reduction plan is illustrated through an example of a gear manufacturing cell. The implications for management are: (1) that pre-established levels for set-up time and batch size reductions are not always effective; and (2) that effective reduction plans need to be preceded by system capacity and performance analysis to determine the effects of such reductions prior to implementation.
引用
收藏
页码:769 / 791
页数:23
相关论文
共 14 条
[1]  
[Anonymous], 1992, MANUFACTURING 90S BE
[2]   CAN A REDUCTION IN SET UP COSTS INDEED INCREASE TOTAL COSTS [J].
GERCHAK, Y .
MANAGEMENT SCIENCE, 1988, 34 (10) :1271-1272
[3]  
Goldratt E.M., 1990, THEORY CONSTRAINTS
[4]  
Hadley G., 1963, ANAL INVENTORY SYSTE
[5]   APPROXIMATE ANALYSIS OF GENERAL QUEUING NETWORKS BY DECOMPOSITION [J].
KUEHN, PJ .
IEEE TRANSACTIONS ON COMMUNICATIONS, 1979, 27 (01) :113-126
[6]   SEQUENTIAL PROCEDURE FOR DETERMINING THE LENGTH OF A STEADY-STATE SIMULATION [J].
LAW, AM ;
CARSON, JS .
OPERATIONS RESEARCH, 1979, 27 (05) :1011-1025
[7]   ON THE APPROXIMATIONS TO THE SINGLE-SERVER QUEUE [J].
SHANTHIKUMAR, JG ;
BUZACOTT, JA .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1980, 18 (06) :761-773
[8]   SETUP REDUCTION AND INCREASED EFFECTIVE CAPACITY [J].
SPENCE, AM ;
PORTEUS, EL .
MANAGEMENT SCIENCE, 1987, 33 (10) :1291-1301
[9]  
Suri R., 1993, HDB OR MS, V4, P199
[10]  
Thesen A., 1992, SIMULATION DECISION