The terms of concession including tariff and concession period are often discussed intensively during negotiations of build-operate-transfer (BOT) contracts. Based on prior studies on negotiation terms and risk of BOT contracts, this paper incorporates risk attributes of the BOT project into the formulation of a contractual-negotiation model. The proposed model allows the government and the sponsor to reach a consensus on the terms should the financial return as well as the risk of the project be determined. The pro forma cash flow of a BOT project is developed and used to generate the probability distribution of net present values (NPV) from the owner's viewpoint by using Monte Carlo simulation. High- and low-risk scenarios are obtained to determine whether the contractual-negotiation models vary in accordance with risk levels. Results show that, given the expected NPV, the sponsor should be offered more favorable concessional terms for projects with high risk than that with low risk. We suggest that the government and industry practitioners embody the risk attributes of the project in the automated contractual-negotiation model.
引用
收藏
页码:18 / 24
页数:7
相关论文
共 23 条
  • [1] DEBT CAPACITY AND OPTIMAL CAPITAL STRUCTURE FOR PRIVATELY FINANCED INFRASTRUCTURE PROJECTS
    DIAS, A
    IOANNOU, PG
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1995, 121 (04): : 404 - 414
  • [2] HERTZ DB, 1964, HARVARD BUS REV, V42, P95
  • [3] Hoffman P., 1998, The Man Who Loved Only Numbers: The Story of Paul Erdos and the Search for Mathematical Truth
  • [4] Build-operate-transfer-type procurement in Asian megaprojects
    Kumaraswamy, MM
    Morris, DA
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2002, 128 (02) : 93 - 102
  • [5] Critical success factors for PPP/PFI projects in the UK construction industry
    Li, Bing
    Akintoye, A.
    Edwards, P. J.
    Hardcastle, C.
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2005, 23 (05) : 459 - 471
  • [6] Privatization decision and civil engineering projects
    Liddle, BT
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 1997, 13 (03) : 73 - 78
  • [7] MALIK R, 1999, CONSTR MANAGE EC, V17, P613
  • [8] Build operate transfer municipal bridge projects in India
    Malini, E
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 1999, 15 (04) : 51 - 58
  • [9] THE MONTE CARLO METHOD
    METROPOLIS, N
    ULAM, S
    [J]. JOURNAL OF THE AMERICAN STATISTICAL ASSOCIATION, 1949, 44 (247) : 335 - 341
  • [10] Automated approach to negotiation of BOT contracts
    Ngee, L
    Tiong, RLK
    Alum, J
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (02) : 121 - 128