Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities

被引:163
作者
Lambrechts, Olivier [1 ]
Demeulemeester, Erik [1 ]
Herroelen, Willy [1 ]
机构
[1] Katholieke Univ Leuven, Fac Econ & Appl Econ, Res Ctr Operat Management, Dept Decis Sci & Informat Management, Louvain, Belgium
关键词
proactive/reactive project scheduling; stochastic resource breakdowns;
D O I
10.1007/s10951-007-0021-0
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Research concerning project planning under uncertainty has primarily focused on the stochastic resource-constrained project scheduling problem (stochastic RCPSP), an extension of the basic RCPSP, in which the assumption of deterministic activity durations is dropped. In this paper, we introduce a new variant of the RCPSP, for which the uncertainty is modeled by means of resource availabilities that are subject to unforeseen breakdowns. Our objective is to build a robust schedule that meets the project deadline and minimizes the schedule instability cost, defined as the expected weighted sum of the absolute deviations between the planned and the actually realized activity starting times during project execution. We describe how stochastic resource breakdowns can be modeled, which reaction is recommended, when a resource infeasibility occurs due to a breakdown, and how one can protect the initial schedule from the adverse effects of potential breakdowns. An extensive computational experiment is used to show the relative performance of the proposed proactive and reactive strategies. It is shown that protection of the baseline schedule, coupled with intelligent schedule recovery, yields significant performance gains over the use of deterministic scheduling approaches in a stochastic setting.
引用
收藏
页码:121 / 136
页数:16
相关论文
共 27 条
[1]   A bi-objective model for robust resource-constrained project scheduling [J].
Al-Fawzan, MA ;
Haouari, M .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2005, 96 (02) :175-187
[2]  
[Anonymous], 2001, THESIS TU BERLIN BER
[3]   Executing production schedules in the face of uncertainties: A review and some future directions [J].
Aytug, H ;
Lawley, MA ;
McKay, K ;
Mohan, S ;
Uzsoy, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 161 (01) :86-110
[4]   Resource-constrained project scheduling: Notation, classification, models, and methods [J].
Brucker, P ;
Drexl, A ;
Mohring, R ;
Neumann, K ;
Pesch, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (01) :3-41
[5]  
DAVENPORT A, 2002, UNPUB SURVEY TECHNIQ
[6]   A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM [J].
DEMEULEMEESTER, E ;
HERROELEN, W .
MANAGEMENT SCIENCE, 1992, 38 (12) :1803-1818
[7]  
Demeulemeester E, 2002, INT SERIES OPERATION, V49
[8]   New benchmark results for the resource - Constrained project scheduling problem [J].
Demeulemeester, EL ;
Herroelen, WS .
MANAGEMENT SCIENCE, 1997, 43 (11) :1485-1492
[9]  
DREZET LE, 2005, THESIS U FRANCOIS RA
[10]  
GIRAULT M, 1959, INITIATION PROCESSUS