Production quotas as bounds on interplant JIT contracts

被引:18
作者
Duenyas, I [1 ]
Hopp, WJ [1 ]
Bassok, Y [1 ]
机构
[1] NORTHWESTERN UNIV, DEPT IND ENGN & MANAGEMENT SCI, EVANSTON, IL 60208 USA
关键词
pull systems; just-in-time; production control; supply chain management;
D O I
10.1287/mnsc.43.10.1372
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
We consider the situation of a supplier plant whose customer plants desire just-in-time (JIT) deliveries. Randomness in both the production and demand processes make satisfying every demand that might occur in true JIT fashion impossible. Therefore, supplier plants typically negotiate bounds on JIT contracts with their customers. In this paper, we focus on the use Of ''quotas'' or ''target inventory levels'' as a mechanism for establishing such bounds. That is, the supplier firm is responsible for meeting periodic demands up to the quota, but not beyond. In this paper, we consider the problem of setting an appropriate quota from the perspective of the supplier plant and interpret our results in the context of the negotiation process between the supplier and its customers. Under the assumption that ''safety capacity'' (i.e., overtime or a vendoring option) is available, we develop two models that address this problem. The first model assumes that quota shortfalls cannot be carried over to the next regular time production period and are made up with overtime/vendoring, which incurs fixed plus variable costs. The second model assumes that shortages can be backlogged to the next regular time production period at a cost. We use numerical examples to demonstrate how the models we developed were used by a clutch supplier to a large auto manufacturer to negotiate its JIT contracts.
引用
收藏
页码:1372 / 1386
页数:15
相关论文
共 22 条
[1]  
Arrow K.J., 1958, Studies in the Mathematical Theory of Inventory and Production
[2]  
Barankin EW., 1961, NAVAL RES LOGIST Q, V8, P285, DOI DOI 10.1002/NAV.3800080310
[3]  
BENSOUSSAN A, 1982, MATH THEORY PRODUCTI
[4]   OPTIMALITY OF ZERO-INVENTORY POLICIES FOR UNRELIABLE MANUFACTURING SYSTEMS [J].
BIELECKI, T ;
KUMAR, PR .
OPERATIONS RESEARCH, 1988, 36 (04) :532-541
[5]   HIERARCHICAL PRODUCTION PLANNING - A 2-STAGE SYSTEM [J].
BITRAN, GR ;
HAAS, EA ;
HAX, AC .
OPERATIONS RESEARCH, 1982, 30 (02) :232-251
[6]   A PERIODIC REVIEW, PRODUCTION PLANNING-MODEL WITH UNCERTAIN CAPACITY AND UNCERTAIN DEMAND - OPTIMALITY OF EXTENDED MYOPIC POLICIES [J].
CIARALLO, FW ;
AKELLA, R ;
MORTON, TE .
MANAGEMENT SCIENCE, 1994, 40 (03) :320-332
[7]  
DANIEL KH, 1963, MULTISTATE INVENTORY
[8]   CHARACTERIZING THE OUTPUT PROCESS OF A CONWIP LINE WITH DETERMINISTIC PROCESSING AND RANDOM OUTAGES [J].
DUENYAS, I ;
HOPP, WJ ;
SPEARMAN, ML .
MANAGEMENT SCIENCE, 1993, 39 (08) :975-988
[9]   CONWIP ASSEMBLY WITH DETERMINISTIC PROCESSING AND RANDOM OUTAGES [J].
DUENYAS, I ;
HOPP, WJ .
IIE TRANSACTIONS, 1992, 24 (04) :97-109
[10]  
Duenyas I., 1993, Queueing Systems Theory and Applications, V14, P135, DOI 10.1007/BF01153531