Scheduling jobs with different, job-dependent earliness and tardiness penalties using the SLK method

被引:11
作者
Adamopoulos, GI [1 ]
Pappis, CP [1 ]
机构
[1] UNIV PIRAEUS,DEPT IND MANAGEMENT,GR-18534 PIRAEUS,GREECE
关键词
due date; weighted lateness; slack time; scheduling;
D O I
10.1016/0377-2217(94)00191-X
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
The single machine job scheduling problem, where due dates are assigned using the SLK due date determination method, is examined assuming different penalties for the early and tardy jobs. These penalties are assumed to be job-dependent, proportional to the processing times of jobs raised to an integer, non-negative power. The objective function is the total weighted lateness. Several cases are examined and four algorithms providing the optimal sequences for these cases are presented. Examples are given and conclusions are drawn.
引用
收藏
页码:336 / 344
页数:9
相关论文
共 22 条
[1]   THE CON DUE-DATE DETERMINATION METHOD WITH PROCESSING TIME-DEPENDENT LATENESS PENALTIES [J].
ADAMOPOULOS, GI ;
PAPPIS, CP .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 1995, 40 (01) :29-36
[2]   MINIMIZING MEAN SQUARED DEVIATION OF COMPLETION TIMES ABOUT A COMMON DUE DATE [J].
BAGCHI, U ;
SULLIVAN, RS ;
CHANG, YL .
MANAGEMENT SCIENCE, 1987, 33 (07) :894-906
[3]   ON THE ASSIGNMENT OF OPTIMAL DUE DATES [J].
BAKER, KR ;
SCUDDER, GD .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1989, 40 (01) :93-95
[4]   SEQUENCING WITH EARLINESS AND TARDINESS PENALTIES - A REVIEW [J].
BAKER, KR ;
SCUDDER, GD .
OPERATIONS RESEARCH, 1990, 38 (01) :22-36
[5]   DETERMINATION OF AN OPTIMAL COMMON DUE DATE AND OPTIMAL SEQUENCE IN A SINGLE-MACHINE JOB SHOP [J].
BECTOR, CR ;
GUPTA, YP ;
GUPTA, MC .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1988, 26 (04) :613-628
[6]   SURVEY OF SCHEDULING RESEARCH INVOLVING DUE DATE DETERMINATION DECISIONS [J].
CHENG, TCE ;
GUPTA, MC .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1989, 38 (02) :156-166
[7]  
CHENG TCE, 1984, J OPER RES SOC, V35, P433
[8]  
CHENG TCE, 1989, J OPER RES SOC, V40, P1129, DOI 10.1057/palgrave.jors.0401208
[9]   OPTIMAL CONSTANT DUE-DATE DETERMINATION AND SEQUENCING OF N-JOBS ON A SINGLE-MACHINE [J].
CHENG, TCE .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 1991, 22 (03) :259-261
[10]  
CHENG TCE, 1985, ENG OPTIM, V9, P127, DOI DOI 10.1080/03052158508902508