Integrated production and material handling scheduling using mathematical programming and constraint programming

被引:84
作者
El Khayat, Ghada
Langevin, Andre
Riopel, Diane
机构
[1] Ecole Polytech Montreal, Montreal, PQ H3C 3A7, Canada
[2] Gerad, Montreal, PQ H3C 3A7, Canada
关键词
scheduling; job shop; material handling; mixed integer programming; constraint programming;
D O I
10.1016/j.ejor.2005.02.077
中图分类号
C93 [管理学];
学科分类号
12 [管理学]; 1201 [管理科学与工程]; 1202 [工商管理学]; 120202 [企业管理];
摘要
In this article, we propose an integrated formulation of the combined production and material handling scheduling problems. Traditionally, scheduling problems consider the production machines as the only constraining resource. This is however no longer true as material handling vehicles are becoming more and more valuable resources requiring important investments. Their operations should be optimized and above all synchronized with machine operations. In the problem addressed in this paper, a job shop context is considered. Machines and vehicles are both considered as constraining resources. The integrated scheduling problem is formulated as a mathematical programming model and as a constraint programming model which are compared for optimally solving a series of test problems. A commercial software (ILOG OPLStudio) was used for modeling and testing both models. (c) 2005 Elsevier B.V. All rights reserved.
引用
收藏
页码:1818 / 1832
页数:15
相关论文
共 26 条
[1]
THE SHIFTING BOTTLENECK PROCEDURE FOR JOB SHOP SCHEDULING [J].
ADAMS, J ;
BALAS, E ;
ZAWACK, D .
MANAGEMENT SCIENCE, 1988, 34 (03) :391-401
[2]
[Anonymous], LOGIC BASED METHODS
[3]
Integrated scheduling of material handling and manufacturing activities for just-in-time production of complex assemblies [J].
Anwar, MF ;
Nagi, R .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1998, 36 (03) :653-681
[4]
ANWAR MF, 1997, P 1997 6 ANN IND ENG
[5]
Baptiste P., 2001, CONSTRAINT BASED SCH
[6]
BEASLEY JE, OR LIB TEST PROBLEMS
[7]
A time window approach to simultaneous scheduling of machines and material handling system in an FMS [J].
Bilge, U ;
Ulusoy, G .
OPERATIONS RESEARCH, 1995, 43 (06) :1058-1070
[8]
ELKHAYAT G, 2003, THESIS ECOLE POLYTEC
[9]
JAIN V, 2001, INFORMS J COMPUTING, V13
[10]
AGV schedule integrated with production in flexible manufacturing systems [J].
Jawahar, N ;
Aravindan, P ;
Ponnambalam, SG ;
Suresh, RK .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 1998, 14 (06) :428-440