decomposition heuristics;
rescheduling;
global schedules;
semiconductor manufacturing;
dispatching;
simmulation;
D O I:
10.1080/00207540412331282024
中图分类号:
T [工业技术];
学科分类号:
08 ;
摘要:
The problem of implementing global factory schedules developed from all optimization-based heuristic in a manufacturing facility with executional uncertainties in the form of machine failures is considered. A simple procedure in which jobs Lire dispatched on the shop floor is proposed based oil their start times in the global schedule is proposed. The performance of the proposed procedure relative to a number of well-known dispatching rules is evaluated using a simulation model of a scaled-down semiconductor wafer fabrication facility. Results indicate that the procedure combining the global schedule and dispatching outperforms the benchmark dispatching rules in terms of several performance measures as long as the level of variability in the system is compatible with the frequency of rescheduling.