Production scheduling in a steelmaking-continuous casting plant

被引:139
作者
Pacciarelli, D [1 ]
Pranzo, M [1 ]
机构
[1] Univ Roma Tre, Dipartimento & Automazione, I-00146 Rome, Italy
关键词
scheduling; production planning; steelmaking;
D O I
10.1016/j.compchemeng.2004.08.031
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In this paper we describe an optimization procedure for planning the production of steel ingots in a steel making-continuous casting plant. The strict requirements of the production process defeated most of the earlier approaches to steelmaking-continuous casting production scheduling. mainly due to the lack of information in the optimization models. Our formulation of the problem is based on the alternative graph, which is a generalization of the disjunctive graph of Roy and Sussman. The alternative graph formulation allow us to describe in detail all the constraints that are relevant for the scheduling problem. We then solve the problem by using a beam search procedure, and compare our results with a lower bound of the optimal solutions and with the actual performance obtained in the plant. Computational experience shows the effectiveness of this approach. (C) 2004 Elsevier Ltd. All rights reserved.
引用
收藏
页码:2823 / 2835
页数:13
相关论文
共 37 条
[1]   Batch scheduling in a two-machine flow shop with limited buffer [J].
Agnetis, A ;
Pacciarelli, D ;
Rossi, F .
DISCRETE APPLIED MATHEMATICS, 1997, 72 (03) :243-260
[2]   PREDICTING DEADLOCK IN STORE-AND-FORWARD NETWORKS [J].
ARBIB, C ;
ITALIANO, GF ;
PANCONESI, A .
NETWORKS, 1990, 20 (07) :861-881
[3]  
Balas Egon., 1979, ANN OFDISCRETE MATH, V5, P3, DOI DOI 10.1016/S0167-5060(08)70342-X
[4]   ADJUSTMENT OF HEADS AND TAILS FOR THE JOB-SHOP PROBLEM [J].
CARLIER, J ;
PINSON, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1994, 78 (02) :146-161
[5]   THE ONE-MACHINE SEQUENCING PROBLEM [J].
CARLIER, J .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1982, 11 (01) :42-47
[6]   AN ALGORITHM FOR SOLVING THE JOB-SHOP PROBLEM [J].
CARLIER, J ;
PINSON, E .
MANAGEMENT SCIENCE, 1989, 35 (02) :164-176
[7]  
Carlier J., 1990, Annals of Operations Research, V26, P269
[8]   Comparison of iterative improvement techniques for schedule optimization [J].
Dorn, J ;
Girsch, M ;
Skele, G ;
Slany, W .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 94 (02) :349-361
[9]   Scheduling high-grade steelmaking [J].
Dorn, J ;
Shams, R .
IEEE EXPERT-INTELLIGENT SYSTEMS & THEIR APPLICATIONS, 1996, 11 (01) :28-35
[10]  
DUTTA G, 2001, MANUFACTURING SERVIC, V3, P387, DOI DOI 10.1287/MSOM.3.4.387.9972