Task assignment with multiskilled employees and multiple modes for product development projects

被引:4
作者
Hui Cheng
Xuening Chu
机构
[1] Shanghai Jiao Tong University,School of Mechanical Engineering
来源
The International Journal of Advanced Manufacturing Technology | 2012年 / 61卷
关键词
Task assignment; Product development project; Multiskilled employees; Multiple execution modes;
D O I
暂无
中图分类号
学科分类号
摘要
In a product development project, efficiently assigning tasks to employees is difficult, since high level of design imprecision and employees with multiple skills and different skill levels exist. The relative skill levels of employees are modeled by fuzzy numbers, and membership function is introduced to describe the confidential levels of the duration the task takes. The employees’ workloads in the project are calculated based on fuzzy sets theory and design structure matrix, and then multiple execution modes are generated by assigning different employees to the tasks. An optimization model of task assignment problem, which incorporates some factors not previously considered together (multiskilled employees and their skill levels, task iteration and the precedence constraints), is proposed. The objective function considered is to minimize the duration of the project and balance the workloads of the employees attending the project. Based on the information above, a genetic algorithm is utilized to find the optimum solution with regards to the considered objectives. A case of a die product development project is used to illustrate the problem and proposed method. The results verify the feasibility and effectiveness of this algorithm.
引用
收藏
页码:391 / 403
页数:12
相关论文
共 44 条
  • [1] Zamani R(2010)A parallel complete anytime procedure for project scheduling under multiple resource constraints Int J Adv Manuf Technol 44 1-10
  • [2] Sabzehparvar M(2008)A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags J Supercomput 44 257-273
  • [3] Seyed-Hosseini S(2004)A fuzzy robust scheduling approach for product development projects Eur J Oper Res 152 180-194
  • [4] Wang J(1996)On-line control model for cost simulation network projects J Oper Res Soc 47 266-283
  • [5] Golenko-Ginzburg D(1981)The design structure system: a method for managing the design of complex systems IEEE Trans Eng Manag 28 71-74
  • [6] Gonik A(1997)A predictive model of sequential iteration in engineering design Manag Sci 43 1104-1120
  • [7] Steward DV(2001)Applying the design structure matrix to system decomposition and integration problems: a review and new directions IEEE Trans Eng Manag 48 292-306
  • [8] Smith RP(1994)A model based method for organizing tasks in product development Res Eng Des 6 1-13
  • [9] Eppinger SD(1999)Engineering design management: an information structure approach Int J Prod Res 37 2957-2975
  • [10] Browning TR(2000)Re-engineering of the design process for concurrent engineering Comput Ind Eng 38 479-491