SIMULATION OF LEARNING DEVELOPMENT IN REPETITIVE CONSTRUCTION

被引:36
作者
LUTZ, JD
HALPIN, DW
WILSON, JR
机构
[1] Dept. of Civ. Engrg., Auburn Univ., Auburn
[2] Div. of Constr. Engrg. and Mgmt, Purdue Univ., West Lafayette
[3] Dept. of Industrial Engrg., North Carolina State Univ., Raleigh
来源
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE | 1994年 / 120卷 / 04期
关键词
D O I
10.1061/(ASCE)0733-9364(1994)120:4(753)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper presents the methodology used to model the learning development phenomenon in the CYCLONE format using the Boeing learning curve. The learning development enhancement was coded in the MicroCYCLONE (a microcomputer version of CYCLONE) environment using QuickBASIC programming. The enhancement allows the user to specify the rate of learning expressed as a percentage, the realization count required for the task duration to increment due to learning, and the threshold at which no more learning improvement can be realized. The existing routines for generating deterministic durations and stochastic durations based on uniform, triangular, and beta distributions were upgraded to calculate durations that reflect the impact of learning development. The learning development enhancement can be extended for use with other simulation programs based on the CYCLONE modeling format. The developed learning-development enhancement was used to model and simulate the learning-development phenomenon for linear construction operation illustrative examples. Findings from the simulation experimentation performed for the illustrative examples are provided. The significance, capabilities, and implementation of the learning-development enhancement are discussed.
引用
收藏
页码:753 / 773
页数:21
相关论文
共 15 条
[1]  
Alden R., Learning curves: An example, Industrial Engrg, 6, 12, pp. 34-37, (1974)
[2]  
Carlson J., Cubic learning curves: Precision tool for labor estimating, Manufacturing Engrg. and Mgmt., pp. 22-25, (1973)
[3]  
Chang D.Y., RESQUE: A resource based simulation system for construction process planning, (1986)
[4]  
Cochran E., New concept of the learning curve, J. Industrial Engrg, pp. 317-327, (1960)
[5]  
Cunningham J., Using the learning curve as a management tool, IEEE Spectrum, pp. 45-48, (1980)
[6]  
Halpin D.W., An investigation of the use of simulation networks for modeling construction operations, (1973)
[7]  
Halpin D.W., Microcyclone User’s Manual, (1990)
[8]  
Hijazi A., Simulation analysis of linear construction processes, (1989)
[9]  
Ioannou P.G., UM-CYCLONE User’s Guide, (1989)
[10]  
Kalk A., INSIGHT-interactive simulation of construction operations using graphical techniques, Tech. Rep. No. 238, (1980)