Risk-minimizing approach to bid-cutting limit determination

被引:19
作者
Chao, Li-Chung [1 ]
Liou, Chang-Nan [2 ]
机构
[1] Natl Kaohsiung First Univ Sci & Technol, Kaohsiung, Taiwan
[2] Ri Xin Construct Co Ltd, Taoyuan, Taiwan
关键词
Bidding; estimating; probability; Monte Carlo simulation; risk analysis;
D O I
10.1080/01446190701393018
中图分类号
F [经济];
学科分类号
02 ;
摘要
Intense price competition is quite common in the construction industry. In many markets, contractors have to cut their bids to compete, giving priority to winning enough contracts to sustain normal operation, and it is common to see a winning bid close to the expected project cost. While cutting bids not only gives up profits but also undoubtedly increases the risk of making a loss, the behaviour of contractors in intense competition is difficult to explain by existing academic bidding models. An approach to determining the lower limit of the bid for a project is proposed based on minimization of the overall loss risk defined by a probabilistic model. The approach can be used to prevent arbitrary over-cuts in final bid decision where price competition is intense. Factors influencing the suggested bid-cutting limit for a project are analysed. An illustrative example using real case data is provided.
引用
收藏
页码:835 / 843
页数:9
相关论文
共 11 条
  • [1] OPTIMUM MARK-UP FOR BIDDING - A PREFERENCE-UNCERTAINTY TRADE OFF APPROACH
    AHMAD, I
    MINKARAH, IA
    [J]. CIVIL ENGINEERING SYSTEMS, 1987, 4 (04): : 170 - 174
  • [2] Defining triangular probability distributions from historical cost data
    Back, WE
    Boles, WW
    Fry, GT
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2000, 126 (01): : 29 - 37
  • [3] CARR RI, 1982, J CONSTRUCT DIV-ASCE, V108, P639
  • [4] Chao Li-Chung, 2000, Proceedings of the 17th IAARC/CIB/IEEE/IFR International Symposium on Automation and Robotics in Construction. 17th ISAREC 2000, P777
  • [5] PROBABILISTIC ESTIMATING - MATHEMATICS AND APPLICATIONS
    DIEKMANN, JE
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1983, 109 (03): : 297 - 308
  • [6] Utility-theory model for markup decisions
    Dozzi, SP
    AbouRizk, SM
    Schroeder, SL
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (02): : 119 - 124
  • [7] Gates M., 1967, ASCE J CONSTRUCTION, V93, P75
  • [8] Role of marketing intelligence in making pricing policy in construction
    Mochtar, K
    Arditi, D
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2001, 17 (03) : 140 - 148
  • [9] DBID - ANALOGY-BASED DSS FOR BIDDING IN CONSTRUCTION
    MOSELHI, O
    HEGAZY, T
    FAZIO, P
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1993, 119 (03): : 466 - 479
  • [10] Palisade, 2000, GUID US RISK RISK AN