We address single and multiple machine versions of the batch scheduling problem which arises when there are job families and setup requirements between these families; our aim is to minimize the total of the completion or weighted completion times. The observations provided by us extend past results.
引用
收藏
页码:271 / 275
页数:5
相关论文
共 14 条
[1]   SINGLE FACILITY MULTICLASS JOB SCHEDULING [J].
AHN, BH ;
HYUN, JH .
COMPUTERS & OPERATIONS RESEARCH, 1990, 17 (03) :265-272
[2]   BATCHING TO MINIMIZE FLOW TIMES ON ONE MACHINE [J].
DOBSON, G ;
KARMARKAR, US ;
RUMMEL, JL .
MANAGEMENT SCIENCE, 1987, 33 (06) :784-799
[3]   BATCHING TO MINIMIZE FLOW TIMES ON PARALLEL HETEROGENEOUS MACHINES [J].
DOBSON, G ;
KARMARKAR, US ;
RUMMEL, JL .
MANAGEMENT SCIENCE, 1989, 35 (05) :607-613
[4]  
Garey MR., 1979, COMPUTERS INTRACTABI
[5]   SINGLE FACILITY SCHEDULING WITH MULTIPLE JOB CLASSES [J].
GUPTA, JND .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1988, 33 (01) :42-45
[6]   OPTIMAL SCHEDULES FOR SINGLE FACILITY WITH 2 JOB CLASSES [J].
GUPTA, JND .
COMPUTERS & OPERATIONS RESEARCH, 1984, 11 (04) :409-413
[7]  
HAM I, 1985, GROUP TECHNOLOGY APP
[8]   ON THE COMPLEXITY OF SCHEDULING WITH BATCH SETUP TIMES [J].
MONMA, CL ;
POTTS, CN .
OPERATIONS RESEARCH, 1989, 37 (05) :798-804
[9]  
Nemhauser G. L., 1988, INTEGER COMBINATORIA
[10]   INTEGRATING SCHEDULING WITH BATCHING AND LOT-SIZING - A REVIEW OF ALGORITHMS AND COMPLEXITY [J].
POTTS, CN ;
VANWASSENHOVE, LN .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1992, 43 (05) :395-406