MINIMIZING THE TOTAL FLOW TIME OF N JOBS ON A NETWORK

被引:46
作者
SIMCHILEVI, D [1 ]
BERMAN, O [1 ]
机构
[1] UNIV TORONTO,DEPT MANAGEMENT,TORONTO M5S 1A1,ONTARIO,CANADA
关键词
D O I
10.1080/07408179108963858
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper addresses the problem of determining a sequence for processing jobs on a machine, with sequence dependent setup times, such that the total flow time is minimized. The paper includes a branch and bound algorithm to find the optimal tour sequence.
引用
收藏
页码:236 / 244
页数:9
相关论文
共 10 条
[1]  
Baker K., 1974, INTRO SEQUENCING SCH
[2]   MINISUM LOCATION OF A TRAVELING SALESMAN [J].
BERMAN, O ;
LEVI, DS .
NETWORKS, 1986, 16 (03) :239-254
[3]   DYNAMIC REPOSITIONING OF INDISTINGUISHABLE SERVICE UNITS ON TRANSPORTATION NETWORKS [J].
BERMAN, O .
TRANSPORTATION SCIENCE, 1981, 15 (02) :115-136
[4]  
Dijkstra EW., 1959, NUMER MATH, V1, P269, DOI DOI 10.1007/BF01386390
[5]   AN APPRAISAL OF SOME SHORTEST-PATH ALGORITHMS [J].
DREYFUS, SE .
OPERATIONS RESEARCH, 1969, 17 (03) :395-&
[6]  
HANDLER G. Y., 1979, LOCATION NETWORKS
[7]  
JAILLET P, 1985, MIT185 OP RES CTR TE
[8]  
MINIEKA E, 1984, 1984 ORSA TIMS SAN F
[9]  
Papadimitriou C. H., 1998, COMBINATORIAL OPTIMI
[10]   P-COMPLETE APPROXIMATION PROBLEMS [J].
SAHNI, S ;
GONZALEZ, T .
JOURNAL OF THE ACM, 1976, 23 (03) :555-565