3 YEARS OF FULL-SCALE CAPTOR(R) PROCESS OPERATION AT MOUNDSVILLE WWTP

被引:16
作者
GOLLA, P
REDDY, MP
SIMMS, MK
LAKEN, TJ
机构
[1] POST BUCKLEY SCHUH & JERNIGAN INC,MIAMI,FL 32789
[2] MOUNDSVILLE GLENDALE WWTP,MOUNDSVILLE,WV 26041
关键词
MOUNDSVILLE; NITRIFICATION; DENITRIFICATION; BOD5; REMOVAL; CAPTOR(R) PROCESS; SLUDGE AGE; HYDRAULIC RETENTION TIME;
D O I
10.2166/wst.1994.0759
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Three years of full-scale operation of the Captor(R) process had been completed at the Moundsville/Glen Dale Wastewater Treatment Plant (WWTP) treating a design flow of 8706 m(3)/d (2.3 mgd). The Captor(R) process applied a combination of attached and suspended growth processes by adding polyurethane foam media to activated sludge process, raising the equivalent MLSS concentration. The Captor(R) system was designed as a separate front portion of the activated sludge process, with one third of the total HRT of the activated sludge process. The suspended MLSS in the Captor basin was around 900-1700 mg/L and the equivalent media based attached MLSS was maintained at 6,500-12,000 mg/L. It has been found that soluble CBOD5 removal, nitrification and partial denitrification occurred simultaneously in the Captor basin. The influent loadings to the Captor chamber were at 100-130 mg/L of soluble BOD5, 20-30 mg/L NH3-N, and 50-70 mg/L of TSS at flow rates of 5678-10031 m(3)/d (1.5-2.65 mgd). Over the last three years, 95% soluble CBOD5 removal, 70-90% nitrification and 40-60% denitrification were achieved at an HRT of 50-90 minutes in the Captor chamber. The plant effluent characteristics consistently met 2-4 mg/L of CBOD5, 1-4 mg/L of TSS, and 2-4 mg/L of Ammonia at low temperatures of 12 degrees C-15 degrees C. The HRTs were 2.5-5 hours for secondary aeration with a sludge age of 3-5 days for the activated sludge portion.
引用
收藏
页码:175 / 181
页数:7
相关论文
共 4 条
[1]  
GOLLA PS, 1991, 46TH P IND WAST C, P631
[2]   SIMULTANEOUS REMOVAL OF BOD AND NITROGEN WITH ANOXIC OXIC POROUS BIOMASS SUPPORT SYSTEMS [J].
KONDO, M ;
HOZO, S ;
INAMORI, Y .
WATER SCIENCE AND TECHNOLOGY, 1992, 26 (9-11) :2003-2006
[3]  
THARP CE, 1986, 59TH WPCF C LOS ANG
[4]  
1989, DEMONSTRATION EVALUA