BOUNDS ON EXPECTED PROJECT TARDINESS

被引:20
作者
BIRGE, JR [1 ]
MADDOX, MJ [1 ]
机构
[1] FORD MOTOR CO,DEARBORN,MI 48121
关键词
D O I
10.1287/opre.43.5.838
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A frequent goal in scheduling projects and production operations is determining the financial impact of project duration or production lead time. This paper considers net project value effects that increase proportionally to time in excess of a deadline. New bounds on the expected value of these tardiness costs are given. The bounds provide robust measurements without requiring extensive assumptions about activity distributions.