ELECTRICAL RESYNCHRONIZING OF A LARGE CROSS-COMPOUND TURBINE-GENERATOR SET .2. FIELD TESTS

被引:5
作者
LEVINE, DL
LAY, RK
TEMOSHOK, M
机构
[1] Commonwealth Edison Company, Chicago
[2] General Electric Company, Schenectady
来源
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS | 1969年 / PA88卷 / 07期
关键词
D O I
10.1109/TPAS.1969.292515
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
The procedure for returning a cross-compound set to the line following load rejection and loss of excitation is complicated by the diverging “coast-down” characteristics of the two turbine-generators. The first phase of a resynchronizing procedure is to bring the speeds of the two generators to the same per-unit value. Test results of the resynchronizing process, specifically as it was applied to Commonwealth Edison Company's Will County no. 4 are presented here. The two-pole 332-MVA and four-pole 308-MVA units were successsfully resynchronized from a range of speed differentials up to 0.4 pu by applying rated open-circuit field excitation to one unit. A review of the test results can provide a guide to formulate new operating procedures for resynchronizing of cross-compound generators. These procedures could be established by mutual agreements between utility and manufacturer. Copyright © 1969 by The Institute of Electrical and Electronics Engineers, Inc.
引用
收藏
页码:1146 / &
相关论文
共 4 条
[1]  
BENNER PE, 1957, AIEE T POWER APPARAT, V76, P129
[2]   ELECTRICAL RESYNCHRONIZING OF A LARGE CROSS-COMPOUND TURBINE-GENERATOR SET .I. ANALYTICAL STUDY [J].
LAY, RK ;
LENFEST, EH ;
TEMOSHOK, M ;
WINCHESTER, RL .
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1969, PA88 (07) :1137-+
[3]  
STUVE LR, 1962, AIEE T POWER APPARAT, V81, P748
[4]  
WINCHESTER RL, 1960, JAN IEEE WINT GEN M