OPTIMAL SCHEDULING OF COPRODUCTION WITH A STORAGE

被引:27
作者
RAVN, HF
RYGAARD, JM
机构
[1] Institute of Mathematical Statistics and Operations Research, The Technical University of Denmark, DK-2800, Lyngby
关键词
SCHEDULING; STORAGE; COPRODUCTION; CHP;
D O I
10.1080/03052159408941338
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The problem considered concerns the optimal scheduling of a system with combined heat and power (CHP) units and a heat storage. The purpose of the heat storage is to permit a partial decoupling of the variations in the demand for heat and electrical power. The problem of optimal scheduling is formulated as that of minimizing the total costs over the planning period. The heat demand from the district heating system and the shadow prices for the electrical power system are taken as externally given parameters. The resulting model is solved by dynamic programming. Implementation details and examples of result of the optimization are given.
引用
收藏
页码:267 / 281
页数:15
相关论文
共 13 条
[1]   OPTIMIZING COMBINED COGENERATION AND THERMAL STORAGE-SYSTEMS - AN ENGINEERING ECONOMICS APPROACH [J].
BAUGHMAN, ML ;
EISNER, NA ;
MERRILL, PS .
IEEE TRANSACTIONS ON POWER SYSTEMS, 1989, 4 (03) :974-980
[2]  
DIAMANT R, 1970, TOTAL ENERGY
[3]   HEAT ACCUMULATORS IN CHP NETWORKS [J].
GUSTAFSSON, SI ;
KARLSSON, BG .
ENERGY CONVERSION AND MANAGEMENT, 1992, 33 (12) :1051-1061
[4]  
HANSEN S, 1986, VGB KRAFTWERKSTECHN, V66, P916
[5]  
JEFFS E, 1983, GAS TURBINE WORLD, P42
[6]  
KARKKAINEN S, 1981, 7TH P PSCC C LAUS, P90
[7]  
KARKKAINEN S, 1984, 8TH P PSCC C HELS, P3
[8]  
MOSBECH H, 1983, 1ST IASTED INT S APP
[10]  
RAVN HF, 1992, OPTIMAL COMBINED POW