摘要
The problem of minimizing the completion time variance of n jobs on a single machine has been studied by several authors. We prove the correctness of a 1975 conjecture due to L. Schrage about the position of the third longest job in an optimal schedule.
引用
收藏
页码:467 / 472
页数:6
相关论文
共 5 条
[1]   MINIMIZING WAITING TIME VARIANCE IN SINGLE MACHINE PROBLEM [J].
EILON, S ;
CHOWDHURY, IG .
MANAGEMENT SCIENCE, 1977, 23 (06) :567-575
[2]   MINIMIZING VARIATION OF FLOW TIME IN SINGLE-MACHINE SYSTEMS [J].
KANET, JJ .
MANAGEMENT SCIENCE, 1981, 27 (12) :1453-1459
[3]   VARIANCE MINIMIZATION IN SINGLE MACHINE SEQUENCING PROBLEMS [J].
MERTEN, AG ;
MULLER, ME .
MANAGEMENT SCIENCE SERIES A-THEORY, 1972, 18 (09) :518-528
[4]   MINIMIZING TIME-IN-SYSTEM VARIANCE FOR A FINITE JOBSET [J].
SCHRAGE, L .
MANAGEMENT SCIENCE SERIES A-THEORY, 1975, 21 (05) :540-543
[5]   DETERMINISTIC AND RANDOM SINGLE-MACHINE SEQUENCING WITH VARIANCE MINIMIZATION [J].
VANI, V ;
RAGHAVACHARI, M .
OPERATIONS RESEARCH, 1987, 35 (01) :111-120