摘要
Background, prime influences upon present day methods and current trends in United Kingdom tendering practices are reviewed. Significant weaknesses are identified, confirming the need for some revision of existing contractor selection methods. The findings compliment recommendations of the recent government/Industry review of the construction sector headed by Sir Michael Latham. Specifically, that tendering procedure should embrace investigation of contractors' potential to deliver a service of acceptable standard, on time, within budget. Present selection methods often fail in this objective, being inclined to discriminate predominantly on cost.
引用
收藏
页码:553 / 561
页数:9
相关论文
共 51 条
[1]  
Latham, Constructing The Team, Joint Government/Industry review of procurement and contractual arrangements in the U.K. construction industry, (1994)
[2]  
Odusote, An examination of the importance of resource considerations when contractors make project selection decisions, M.Sc. Dissertation, (1990)
[3]  
Russell, Hancher, Skibniewski, Contractor prequalification data for construction owners, Construction Management & Economics, 10, pp. 117-135, (1992)
[4]  
Holt, Olomolaiye, Harris, Tendering practice—exploring alternatives, Faculty of Building Journal, Nottingham, Autumn, pp. 28-30, (1993)
[5]  
Smith, Estimating and Tendering for Building Work, (1986)
[6]  
Burrows, Tendering in the building industry 1750–1850, M.Phil. Thesis, (1981)
[7]  
Banwell, The Placing and Management of Contracts for Building and Civil Engineering Works, (1964)
[8]  
Holt, Olomolaiye, Harris, A conceptual alternative to current tendering practice, Building Research & Information. The International Journal of Research, Development & Demonstration, 21, 3, pp. 167-172, (1993)
[9]  
N.J.C.C., Code of Tendering Procedure for Industrial Building Works, (1974)
[10]  
N.J.C.C., Code of Procedure for Two Stage Selective Tendering, (1982)