Forecasting construction durations for public housing projects: a Hong Kong perspective

被引:21
作者
Chan, DWM [1 ]
Kumaraswamy, MM [1 ]
机构
[1] Univ Hong Kong, Dept Civil & Struct Engn, Pokfulam Rd, Hong Kong, Peoples R China
关键词
Buildings - Construction - Regression analysis - Standards;
D O I
10.1016/S0360-1323(98)00040-7
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The past thirty years have seen a great surge of international attention and discussion in the domain of 'construction time performance' of building projects. Demand for residential construction has been continually increasing in Hong Kong since the 1950s, while an accelerated demand has been envisaged in the next few years up to 2001. This paper is based on the findings of the third survey in an investigation which aimed at determining a group of critical factors that affect construction durations of building projects in Hong Kong. This stage of the study attempted to generate 'standards' ('norms') for overall completion periods of public housing blocks, by modelling the durations of the primary work packages in the building construction process, i.e. piling, pile caps/raft, superstructure, E&M services, finishes and their respective sequential start-start lag times, in terms of the identified sets of critical factors (significant variables). Data from 15 case studies of standard 'New Cruciform' type housing blocks was collected from the client and contractors. Multiple Linear Regression was applied in analyzing the project data and formulating a construction duration model. The forecasting performance of the model was next evaluated using an independent (new) set of project information from the client, in terms of a relative measure known as the percentage Error. Both the general applications and drawbacks of the model are briefly presented and examined herein. The low values of percentage error (less than about +/- 10%) for overall construction durations confirmed that the model can be a reliable tool for predicting the construction durations of public housing projects in Hong Kong; and the research methodology used could well be extended to similar studies and duration forecasts in other sub-sectors in Hong Kong, as well as in other countries. (C) 1999 Elsevier Science Ltd. All rights reserved.
引用
收藏
页码:633 / 646
页数:14
相关论文
共 32 条
[1]  
BEESTON DT, 1983, STAT METHODS BUILDIN
[2]  
Belsley D., 2005, REGRESSION DIAGNOSTI, V571
[3]  
BLYTH SM, 1995, THESIS U GLAMORGAN U
[4]  
Bromilow F J, 1969, BUILDING FORUM, V1, P70
[5]  
CHAN APC, 1996, THESIS U S AUSTR AUS
[6]   Knowledge building as a mediator of conflict in conceptual change [J].
Chan, C ;
Burtis, J ;
Bereiter, C .
COGNITION AND INSTRUCTION, 1997, 15 (01) :1-40
[7]   An evaluation of construction time performance in the building industry [J].
Chan, DWM ;
Kumaraswamy, MM .
BUILDING AND ENVIRONMENT, 1996, 31 (06) :569-578
[8]  
Chan DWM., 1995, HKIE T, V2, P1
[9]  
CHAN DWM, 1995, CONSTRUCTION MANAGEM, V13, P319, DOI DOI 10.1080/01446199500000037
[10]  
CHAN DWM, 1998, IN PRESS CONSTRUCTIO