NONLINEAR TIME COST TRADEOFF MODELS IN PROJECT-MANAGEMENT

被引:61
作者
DECKRO, RF
HEBERT, JE
VERDINI, WA
GRIMSRUD, PH
VENKATESHWAR, S
机构
[1] UNIV AKRON,COLL BUSINESS,DEPT MANAGEMENT,AKRON,OH 44325
[2] ARIZONA STATE UNIV,COLL BUSINESS,DEPT DECIS & INFORMAT SYST,TEMPE,AZ 85287
[3] POSTENS SENTRALLEDELSE,N-0107 OSLO,NORWAY
关键词
D O I
10.1016/0360-8352(94)00199-W
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In this paper we develop a series of nonlinear time/cost tradeoff models for project management. A base model with quadratic cost relations is developed and then extended to include other operational considerations. The use of nonlinear functions to describe time/cost relationships in project scheduling environments permits a more accurate representation of the operational setting than is possible with linear or piecewise linear approximations. Examples of the models presented are solved directly with commercially available nonlinear programming codes.
引用
收藏
页码:219 / 229
页数:11
相关论文
共 34 条
[1]   NONLINEAR-PROGRAMMING ON GENERALIZED NETWORKS [J].
AHLFELD, DP ;
MULVEY, JM ;
DEMBO, RS ;
ZENIOS, SA .
ACM TRANSACTIONS ON MATHEMATICAL SOFTWARE, 1987, 13 (04) :350-367
[2]  
BERMAN EB, 1964, MANAGE SCI, V10, P724
[3]  
Brooke A., 1988, GAMS USERS GUIDE
[4]   PROJECT SCHEDULING WITH WORK PACKAGES [J].
DECKRO, RF ;
HEBERT, JE ;
VERDINI, WA .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1992, 20 (02) :169-182
[5]   A MULTIPLE OBJECTIVE PROGRAMMING FRAMEWORK FOR TRADEOFFS IN PROJECT SCHEDULING [J].
DECKRO, RF ;
HEBERT, JE .
ENGINEERING COSTS AND PRODUCTION ECONOMICS, 1990, 18 (03) :255-264
[6]  
DECKRO RF, 1989, OMEGA, V17, P106
[7]  
Deckro RF, 1988, J OPNS MGMT, V7, P149
[8]  
DECKRO RF, 1987, 16TH P ANN W DSI M, P134
[9]   LARGE-SCALE NONLINEAR NETWORK MODELS AND THEIR APPLICATION [J].
DEMBO, RS ;
MULVEY, JM ;
ZENIOS, SA .
OPERATIONS RESEARCH, 1989, 37 (03) :353-372
[10]  
ELMAGHRABY SE, 1977, ACTIVITY NETWORKS PR