An algorithm to dynamically adjust the number of Kanbans in stochastic processing times and variable demand environment

被引:61
作者
Gupta, SM
AlTurki, YAY
机构
[1] Departmentof Mechanical, Industrial and Manufacturing Engineering, Northeastern University, Boston, MA, 02115, 330 Snell Engineering Center
关键词
just-in-time (JIT); flexible Kanban system (FKS); processing time variations; demand variation;
D O I
10.1080/095372897235398
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In a real-life environment, the just-in-time (JIT) system is subjected to various types of uncertainties such as stochastic processing times and variable demand. Since, JIT was only meant to operate in a deterministic environment, its performance is seriously affected by variations in processing times and demand. In this paper, a newly developed Kanban system is presented which uses an algorithm to dynamically and systematically manipulate the number of Kanbans in order to offset the blocking and starvation caused by the said uncertainties during a production cycle. The new system is termed a flexible Kanban system (FKS). The steps of the algorithm are detailed and the effectiveness of FKS is demonstrated using an example model. For the example model, the solution procedure, results and a discussion are presented.
引用
收藏
页码:133 / 141
页数:9
相关论文
共 23 条
[1]   DETERMINING THE NUMBER OF KANBANS IN A MULTIPRODUCT, MULTISTAGE PRODUCTION SYSTEM [J].
BARD, JF ;
GOLANY, B .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1991, 29 (05) :881-895
[2]   A MATHEMATICAL-PROGRAMMING APPROACH TO A DETERMINISTIC KANBAN SYSTEM [J].
BITRAN, GR ;
LI, C .
MANAGEMENT SCIENCE, 1987, 33 (04) :427-441
[3]  
Chaturvedi M., 1992, Production Planning and Control, V3, P81, DOI 10.1080/09537289208919376
[4]  
Cheng T. C. E., 1993, Production Planning and Control, V4, P181, DOI 10.1080/09537289308919436
[5]  
Ebrahimpour M., 1985, International Journal of Operations & Production Management, V5, P5, DOI 10.1108/eb054727
[6]   IMPLEMENTATION OF JUST-IN-TIME METHODOLOGY IN A SMALL COMPANY [J].
GUPTA, SM ;
BRENNAN, L .
PRODUCTION PLANNING & CONTROL, 1995, 6 (04) :358-364
[7]   A KNOWLEDGE BASED SYSTEM FOR COMBINED JUST-IN-TIME AND MATERIAL REQUIREMENTS PLANNING [J].
GUPTA, SM ;
BRENNAN, L .
COMPUTERS & ELECTRICAL ENGINEERING, 1993, 19 (02) :157-174
[8]  
GUPTA SM, 1995, P 1995 NE DEC SCI I, P419
[9]   OPTIMAL HYBRID PUSH-PULL CONTROL STRATEGIES FOR A PARALLEL MULTISTAGE SYSTEM .1. [J].
HODGSON, TJ ;
WANG, DW .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1991, 29 (06) :1279-1287
[10]   OPTIMAL HYBRID PUSH-PULL CONTROL STRATEGIES FOR A PARALLEL MULTISTAGE SYSTEM .2. [J].
HODGSON, TJ ;
WANG, DW .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1991, 29 (07) :1453-1460