Tractable nonlinear production planning models for semiconductor wafer fabrication facilities

被引:106
作者
Asmundsson, J [1 ]
Rardin, RL
Uzsoy, R
机构
[1] Straumur Investment Bank, Reykjavik, Iceland
[2] Purdue Univ, Sch Ind Engn, Lab Extended Enterprises, W Lafayette, IN 47907 USA
关键词
cycle times; linear programming; production planning; wafer fabrication;
D O I
10.1109/TSM.2005.863214
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We describe a simulation study of a production planning model for multistage production inventory systems that reflects the nonlinear relationship between resource utilization and lead time. The model is based on the use of clearing functions that capture the nonlinear relationship between workload and throughput. We show how these clearing functions can be estimated from empirical data using a simulation model as a surrogate for observation of the production system under study. We then examine the sensitivity of the estimated clearing function to different dispatching algorithms, different demand patterns, and production planning techniques. Computational experiments based on a scaled-down model of a semiconductor wafer fabrication facility illustrate the potential benefits of the clearing function model relative to conventional linear programming models.
引用
收藏
页码:95 / 111
页数:17
相关论文
共 31 条
[1]  
[Anonymous], 2003, Introduction to Computational Optimization Models for Production Planning in a Supply Chain
[2]  
ASMUNDSSON J., 2002, TRACTABLE NONLINEAR
[3]   MATHEMATICAL-PROGRAMMING APPROACHES TO CAPACITY-CONSTRAINED MRP SYSTEMS - REVIEW, FORMULATION AND PROBLEM REDUCTION [J].
BILLINGTON, PJ ;
MCCLAIN, JO ;
THOMAS, LJ .
MANAGEMENT SCIENCE, 1983, 29 (10) :1126-1141
[4]  
Dauzere-Peres S, 1994, INTEGRATED APPROACH
[5]  
Fleischmann B, 2003, HDBK OPER R, V11, P457
[6]   A TACTICAL PLANNING-MODEL FOR A JOB SHOP [J].
GRAVES, SC .
OPERATIONS RESEARCH, 1986, 34 (04) :522-533
[7]   A GENERAL FRAMEWORK FOR MODELING PRODUCTION [J].
HACKMAN, ST ;
LEACHMAN, RC .
MANAGEMENT SCIENCE, 1989, 35 (04) :478-495
[8]  
Hopp W.J., 2001, Factory Physics, V2nd ed.
[9]   A production planning methodology for semiconductor manufacturing based on iterative simulation and linear programming calculations [J].
Hung, YF ;
Leachman, RC .
IEEE TRANSACTIONS ON SEMICONDUCTOR MANUFACTURING, 1996, 9 (02) :257-269
[10]  
HWANG S, 2005, SINGLE STAGE MULTI P