The trade-off between stability and makespan in resource-constrained project scheduling

被引:117
作者
Van De Vonder, S [1 ]
Demeulemeester, E [1 ]
Herroelen, W [1 ]
Leus, R [1 ]
机构
[1] Katholieke Univ Leuven, Res Ctr Operat Management, B-3000 Louvain, Belgium
关键词
project management; scheduling/sequencing; simulation methods;
D O I
10.1080/00207540500140914
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
During the last decade, considerable research efforts in the project scheduling literature have concentrated on resource-constrained project scheduling under uncertainty. Most of this research focuses on protecting the project due date against disruptions during execution. Few efforts have been made to protect the starting times of intermediate activities. In this paper, we develop a heuristic algorithm for minimizing a stability cost function (weighted sum of deviations between planned and realized activity starting times). The algorithm basically proposes a clever way to scatter time buffers throughout the baseline schedule. We provide an extensive simulation experiment to investigate the trade-off between quality robustness (measured in terms of project duration) and solution robustness (stability). We address the issue whether to concentrate safety time in so-called project and feeding buffers in order to protect the planned project completion time or to scatter safety time throughout the baseline schedule in order to enhance stability.
引用
收藏
页码:215 / 236
页数:22
相关论文
共 26 条
[1]   DAGEN: A generator of testsets for project activity nets [J].
Agrawal, MK ;
Elmaghraby, SE ;
Herroelen, WS .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 90 (02) :376-382
[2]  
ALVAREZVALDES R, 1989, ADV PROJECT SCHEDULI, P134
[3]   A polynomial activity insertion algorithm in a multi-resource schedule with cumulative constraints and multiple modes [J].
Artigues, C ;
Roubellat, F .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2000, 127 (02) :297-316
[4]   Resource-constrained project scheduling: Notation, classification, models, and methods [J].
Brucker, P ;
Drexl, A ;
Mohring, R ;
Neumann, K ;
Pesch, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (01) :3-41
[5]   A RANDOM ACTIVITY NETWORK GENERATOR [J].
DEMEULEMEESTER, E ;
DODIN, B ;
HERROELEN, W .
OPERATIONS RESEARCH, 1993, 41 (05) :972-980
[6]   RanGen: A random network generator for activity-on-the-node networks [J].
Demeulemeester, E ;
Vanhoucke, M ;
Herroelen, W .
JOURNAL OF SCHEDULING, 2003, 6 (01) :17-38
[7]   A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM [J].
DEMEULEMEESTER, E ;
HERROELEN, W .
MANAGEMENT SCIENCE, 1992, 38 (12) :1803-1818
[8]  
Demeulemeester E, 2002, INT SERIES OPERATION, V49
[9]   New benchmark results for the resource - Constrained project scheduling problem [J].
Demeulemeester, EL ;
Herroelen, WS .
MANAGEMENT SCIENCE, 1997, 43 (11) :1485-1492
[10]  
Goldratt E., 1997, CRITICAL CHAIN