Hybrid flowshop scheduling with machine and resource-dependent processing times

被引:87
作者
Behnamian, J. [1 ]
Ghomi, S. M. T. Fatemi [1 ]
机构
[1] Amirkabir Univ Technol, Dept Ind Engn, Tehran 1591634311, Iran
关键词
Hybrid flowshop scheduling; Hybrid metaheuristic; Multi-objective optimization; Resource allocation; Machines with different speeds; Sequence-dependent setup times; POPULATION GENETIC ALGORITHM; PARALLEL MACHINES; COMPLETION-TIME; SETUP TIMES; SHOP; OPTIMIZATION; HEURISTICS; CONSTRAINT;
D O I
10.1016/j.apm.2010.07.057
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Most of research in production scheduling is concerned with the optimization of a single criterion. However the analysis of the performance of a schedule often involves more than one aspect and therefore requires a multi-objective treatment. In this research, with combination of two multiple objective decision-making methods, min-max and weighted techniques, a new solution presentation method and a robust hybrid metaheuristic, we solved sequence-dependent setup time hybrid flowshop scheduling problems. In this paper for reflecting real-world situation adequately, we assume the processing time of each job depends on the speed of machine and amount of resource allocated to each machine at the stage which is processed on it. In formulation of min-max type, the decision-maker can have the flexibility of mixed use of weights and distance parameter in expressing desired improvement on produced Pareto optimal solutions. To minimize makespan and total resource allocation costs, the proposed hybrid approach is robust, fast, and simply structured, and comprises two components: genetic algorithm and a variable neighborhood search. The comparison shows the proposal to be very efficient for different structure instances. (C) 2010 Elsevier Inc. All rights reserved.
引用
收藏
页码:1107 / 1123
页数:17
相关论文
共 57 条
[1]  
Affenzeller M, 2002, LECT NOTES ARTIF INT, V2527, P329
[2]   Using ant colony optimization to solve hybrid flow shop scheduling problems [J].
Alaykyran, Kemal ;
Engin, Orhan ;
Doyen, Alper .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2007, 35 (5-6) :541-550
[3]   Group technology in a hybrid flowshop environment:: A case study [J].
Andrés, C ;
Albarracín, JM ;
Tormo, G ;
Vicens, E ;
García-Sabater, JP .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 167 (01) :272-281
[4]   A flexible flowshop problem with total flow time minimization [J].
Azizoglu, M ;
Çakmak, E ;
Kondakci, S .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2001, 132 (03) :528-538
[5]   A multi-phase covering Pareto-optimal front method to multi-objective scheduling in a realistic hybrid flowshop using a hybrid metaheuristic [J].
Behnamian, J. ;
Ghomi, S. M. T. Fatemi ;
Zandieh, M. .
EXPERT SYSTEMS WITH APPLICATIONS, 2009, 36 (08) :11057-11069
[6]   Hybrid flow shop scheduling with precedence constraints and time lags to minimize maximum lateness [J].
Botta-Genoulaz, V .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2000, 64 (1-3) :101-111
[7]   Two-phase sub population genetic algorithm for parallel machine-scheduling problem [J].
Chang, PC ;
Chen, SH ;
Lin, KL .
EXPERT SYSTEMS WITH APPLICATIONS, 2005, 29 (03) :705-712
[8]  
Chang PC, 2006, LECT NOTES COMPUT SC, V4221, P730
[9]   Minimizing maximum completion time in a proportionate flow shop with one machine of different speed [J].
Choi, Byung-Cheon ;
Yoon, Suk-Hun ;
Chung, Sung-Jin .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 176 (02) :964-974
[10]   A multi-population genetic algorithm to solve multi-objective scheduling problems for parallel machines [J].
Cochran, JK ;
Horng, SM ;
Fowler, JW .
COMPUTERS & OPERATIONS RESEARCH, 2003, 30 (07) :1087-1102