Disassembly sequence plan generation using a branch-and-bound algorithm

被引:113
作者
Güngör, A
Gupta, SM
机构
[1] Northeastern Univ, Dept Mech Ind & Mfg Engn, Lab Responsible Mfg, Snell Engn Ctr 334, Boston, MA 02115 USA
[2] Pamukkale Univ, Coll Engn, Dept Ind Engn, TR-20017 Denizli, Turkey
关键词
D O I
10.1080/00207540010002838
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper presents an approach to generate disassembly sequence plans (DSP) automatically for product recycling and remanufacturing. An algorithm is defined first that generates a geometrically based disassembly precedence matrix (DPM) from a CAD drawing of the product. The DPM is then used to generate a hierarchical disassembly tree (HDT) that represents the feasible DSP. Generation of the HDT, i. e. generation of all feasible DSP, is NP- complete. Thus, to keep the size of the HDT manageable, the branching and bounding processes are controlled using two user-defined variables. The first, w, controls the enumeration of the HDT, while the second, v, controls the bounding procedure in the HDT along with an evaluation function. The evaluation function incorporates tool changes, changes in direction of movement during disassembly along with individual part characteristics (e. g. high- valued parts, parts with hazardous content, etc.). The resulting HDT is called the reduced HDT (RHDT) since it only represents as many (near-) optimum DSP as the size of v. Experimental results demonstrate the applicability and effectiveness of the methodology.
引用
收藏
页码:481 / 509
页数:29
相关论文
共 36 条
  • [1] CAD SYSTEM WITH PRODUCT ASSEMBLY DISASSEMBLY PLANNING FUNCTION
    ARAI, E
    IWATA, K
    [J]. ROBOTICS AND COMPUTER-INTEGRATED MANUFACTURING, 1993, 10 (1-2) : 41 - 48
  • [2] Disassembly path generation to verify the assemblability of mechanical products
    Arai, E
    Uchiyama, N
    Igoshi, M
    [J]. JSME INTERNATIONAL JOURNAL SERIES C-DYNAMICS CONTROL ROBOTICS DESIGN AND MANUFACTURING, 1995, 38 (04): : 805 - 810
  • [3] Askiner Gungor, 1998, P 1998 NE DECISION S, P250
  • [4] DISASSEMBLY SEQUENCES FOR OBJECTS BUILT FROM UNIT CUBES
    BEASLEY, D
    MARTIN, RR
    [J]. COMPUTER-AIDED DESIGN, 1993, 25 (12) : 751 - 761
  • [5] OPERATIONS PLANNING ISSUES IN AN ASSEMBLY DISASSEMBLY ENVIRONMENT
    BRENNAN, L
    GUPTA, SM
    TALEB, KN
    [J]. INTERNATIONAL JOURNAL OF OPERATIONS & PRODUCTION MANAGEMENT, 1994, 14 (09) : 57 - 67
  • [6] A structure-oriented approach to assembly sequence planning
    Chakrabarty, S
    Wolter, J
    [J]. IEEE TRANSACTIONS ON ROBOTICS AND AUTOMATION, 1997, 13 (01): : 14 - 29
  • [7] DEMELLO HLS, 1986, AAAI 86 P 5 NAT C AR
  • [8] AND OR GRAPH REPRESENTATION OF ASSEMBLY PLANS
    DEMELLO, LSH
    SANDERSON, AC
    [J]. IEEE TRANSACTIONS ON ROBOTICS AND AUTOMATION, 1990, 6 (02): : 188 - 199
  • [9] DUTTA D, 1995, J ENG IND-T ASME, V117, P102, DOI 10.1115/1.2803269
  • [10] Representation and selection of assembly sequences in computer-aided assembly process planning
    Gottipolu, RB
    Ghosh, K
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1997, 35 (12) : 3447 - 3465