Determining the optimal lot size for the finite production model with random defective rate, the rework process, and backlogging

被引:158
作者
Chiu, YP [1 ]
机构
[1] Chaoyang Univ Technol, Dept Ind Engn & Management, Taichung 413, Taiwan
关键词
production; manufacturing; reworking; EPQ; production lot size;
D O I
10.1080/03052150310001597783
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper considers the effects of the reworking of defective items on the economic production quantity (EPQ) model with backlogging allowed. The classic EPQ model assumes that manufacturing facility functions perfectly during a production run. However, due to process deterioration or other factors, the production process may shift and produce imperfect quality items. In this study, a random defective rate is considered, and when regular production ends, the reworking of defective items starts immediately. Not all of the defective items are reworked, a portion of them are scrap and are discarded. Repairing and holding cost per reworked item and disposal cost per scrap item are included in the proposed mathematical modelling and analysis. The renewal reward theorem is utilized to deal with the variable cycle length, and the optimal lot size that minimizes the overall costs for the imperfect quality EPQ model is derived where backorders are permitted.
引用
收藏
页码:427 / 437
页数:11
相关论文
共 18 条
[1]  
Aggarwal S. C., 1974, INT J PROD RES, V12, P443, DOI [https://doi.org/10.1080/00207547408919568, DOI 10.1080/00207547408919568]
[2]  
[Anonymous], PRODUCTION INVENTORY
[3]   AN EOQ MODEL WITH RANDOM VARIATIONS IN DEMAND [J].
BRILL, PH ;
CHAOUCH, BA .
MANAGEMENT SCIENCE, 1995, 41 (05) :927-936
[4]   AN ECONOMIC ORDER QUANTITY MODEL WITH DEMAND-DEPENDENT UNIT PRODUCTION COST AND IMPERFECT PRODUCTION PROCESSES [J].
CHENG, TCE .
IIE TRANSACTIONS, 1991, 23 (01) :23-28
[5]   Bounds for production lot sizing with machine breakdowns [J].
Chung, KJ .
COMPUTERS & INDUSTRIAL ENGINEERING, 1997, 32 (01) :139-144
[6]   Production lot sizing with the reworking of imperfect quality items produced [J].
Hayek, PA ;
Salameh, MK .
PRODUCTION PLANNING & CONTROL, 2001, 12 (06) :584-590
[7]   SIMULTANEOUS DETERMINATION OF PRODUCTION CYCLE AND INSPECTION SCHEDULES IN A PRODUCTION SYSTEM [J].
LEE, HL ;
ROSENBLATT, MJ .
MANAGEMENT SCIENCE, 1987, 33 (09) :1125-1136
[8]  
Nahmias S., 2001, PRODUCTION OPERATION, V6
[9]   OPTIMAL LOT SIZING, PROCESS QUALITY IMPROVEMENT AND SETUP COST REDUCTION [J].
PORTEUS, EL .
OPERATIONS RESEARCH, 1986, 34 (01) :137-144
[10]  
Rardin RL., 1998, Optimization in operations research