Scheduling a single batch processing machine with secondary resource constraints

被引:31
作者
Kempf, KG [1 ]
Uzsoy, R
Wang, CS
机构
[1] Intel Corp, Knowledge Applicat Lab, Chandler, AZ 85226 USA
[2] Purdue Univ, Sch Ind Engn, W Lafayette, IN 47907 USA
基金
美国国家科学基金会;
关键词
scheduling; semiconductor manufacturing; batch processing machines; heuristics;
D O I
10.1016/S0278-6125(98)80008-3
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper studies the problems of minimizing total completion time (Sigma C-i) and makespan (Cmax) on a single batch processing machine with job families and secondary resource constraints. The motivation for this problem is the burn-in operation in the final testing stage of semiconductor manufacturing, where both oven capacity and the number of boards available may constrain scheduling decisions. Because both problems are NP-hard, integer programming formulations are developed for special cases and are then used to develop heuristics. Extensive computational experiments show that the heuristics are capable of consistently obtaining good solutions in modest CPU times.
引用
收藏
页码:37 / 51
页数:15
相关论文
共 14 条
[1]  
[Anonymous], 1979, Computers and Intractablity: A Guide to the Theoryof NP-Completeness
[2]   MINIMIZING TOTAL COMPLETION-TIME ON A BATCH PROCESSING MACHINE WITH JOB FAMILIES [J].
CHANDRU, V ;
LEE, CY ;
UZSOY, R .
OPERATIONS RESEARCH LETTERS, 1993, 13 (02) :61-65
[3]   MINIMIZING TOTAL COMPLETION-TIME ON BATCH PROCESSING MACHINES [J].
CHANDRU, V ;
LEE, CY ;
UZSOY, R .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1993, 31 (09) :2097-2121
[4]  
*CPLEX OPT INC, 1992, US CPLEX CAL LIB CPL
[5]  
Dobson G., 1992, BATCH LOADING SCHEDU
[6]   DYNAMIC BATCHING HEURISTIC FOR SIMULTANEOUS PROCESSING [J].
GLASSEY, CR ;
WENG, WW .
IEEE TRANSACTIONS ON SEMICONDUCTOR MANUFACTURING, 1991, 4 (02) :77-82
[7]   EFFICIENT SCHEDULING ALGORITHMS FOR A SINGLE BATCH PROCESSING MACHINE [J].
IKURA, Y ;
GIMPLE, M .
OPERATIONS RESEARCH LETTERS, 1986, 5 (02) :61-65
[8]   EFFICIENT ALGORITHMS FOR SCHEDULING SEMICONDUCTOR BURN-IN OPERATIONS [J].
LEE, CY ;
UZSOY, R ;
MARTINVEGA, LA .
OPERATIONS RESEARCH, 1992, 40 (04) :764-775
[9]  
Pinedo M., 1995, Scheduling: Theory, Algorithms, and Systems, V2nd
[10]   A REVIEW OF PRODUCTION PLANNING AND SCHEDULING MODELS IN THE SEMICONDUCTOR INDUSTRY .2. SHOP-FLOOR CONTROL [J].
UZSOY, R ;
LEE, CY ;
MARTINVEGA, LA .
IIE TRANSACTIONS, 1994, 26 (05) :44-55