Best-value model based on project specific characteristics

被引:45
作者
Abdelrahman, Magdy [1 ]
Zayed, Tarek [2 ]
Elyamany, Ahmed [1 ]
机构
[1] N Dakota State Univ, Dept Civil Engn, Fargo, ND 58105 USA
[2] Concordia Univ, Dept Bldg Civil & Environm Engn, Montreal, PQ H3G 1M7, Canada
关键词
Bids; Contractors; Highway construction; Parameters; Project management;
D O I
10.1061/(ASCE)0733-9364(2008)134:3(179)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Best-value becomes a well known procurement practice in many states in the country. The objective of this transformation from the old practice of lowest bid to best-value is to increase the value added to the project for each dollar added. This paper discusses a new concept of best-value modeling that is unique and tailored to each project. The model uses records of past projects to obtain specific evaluation criteria, from which a best-value score is determined for each contractor. Primary parameters that impact contractor selection are identified and analyzed based on which best-value model is designed. Data are collected from groups of experts in the Minnesota Department of Transportation. Two application methods are used to assess the best-value: (1) the weighted average method; and (2) the analytic hierarchy process. Although the paper is written to assist government agencies in selecting the best contractor(s), the research results shared in this paper are relevant to both academics and practitioners. The paper provides practitioners with a tool for ranking contractors based on best-value and provides academics with selection parameters, a model to evaluate this best-value, and a methodology of quantifying the qualitative effect of subjective factors.
引用
收藏
页码:179 / 188
页数:10
相关论文
共 13 条
[1]  
*FAR, 2005, QUAL REQ 9
[2]   Design-build contract award methods for transportation projects [J].
Gransberg, DD ;
Senadheera, SP .
JOURNAL OF TRANSPORTATION ENGINEERING-ASCE, 1999, 125 (06) :565-567
[3]  
GRANSBERG DD, 1996, T AACE INT ABI INFOR
[4]  
Molenaar K. R., 2006, Preparing for design-build projects
[5]  
Molenaar K.R., 2003, Leadership and Management in Engineering, V3, P137, DOI DOI 10.1061/(ASCE)1532-6748(2003)3:3(137
[6]  
*NAVFAC, 1996, 076 RAM SHP
[7]  
*OFF CONSTR INN CO, 2005, INN CONTR GUID
[8]  
Saaty T.L., 1982, DECISION MAKING LEAD
[9]  
Scott S., 2006, 561 NCHRP NAT RES CO
[10]  
VACURA RJ, 2003, AM BAR ASS FOR CONST