Finance-based scheduling of construction projects using integer programming

被引:74
作者
Elazouni, AM [1 ]
Gab-Allah, AA [1 ]
机构
[1] Zagazig Univ, Fac Engn, Construct Engn Dept, Zagazig, Egypt
来源
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE | 2004年 / 130卷 / 01期
关键词
scheduling; computer programming; construction industry;
D O I
10.1061/(ASCE)0733-9364(2004)130:1(15)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Construction scheduling is the process of devising schemes for sequencing activities. A realistic schedule fulfills the real concerns of users, thus minimizing the chances of schedule failure. The minimization of total project duration has been the concept underlying critical-path method/program evaluation and review technique (CPM/PERT) schedules. Subsequently, techniques including resource management and time-cost trade-off analysis were developed to customize CPM/PERT schedules in order to fulfill users' concerns regarding project resources, cost, and time. However, financing construction activities throughout the course of the project is another crucial concern that must be properly treated otherwise, nonrealistic schedules are to be anticipated. Unless contractors manage to procure adequate cash to keep construction work running according to schedule, the pace of work will definitely be relaxed. Therefore, always keeping scheduled activities in balance with available cash is a potential contribution to producing realistic schedules. This paper introduces an integer-programming finance-based scheduling method to produce financially feasible schedules that balance the financing requirements of activities at any period with the cash available during that same period. The proposed method offers twofold benefits of minimizing total project duration and fulfilling finance availability constraints.
引用
收藏
页码:15 / 24
页数:10
相关论文
共 17 条
[1]  
AHUJA HN, 1976, CONSTRUCTION PERFORM
[2]   PROFIT MEASURES FOR CONSTRUCTION PROJECTS [J].
AU, T ;
HENDRICKSON, C .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (02) :273-286
[3]  
BIRRELL GS, 1980, J CONSTRUCT DIV-ASCE, V106, P389
[4]  
Burns SA., 1996, CONSTR MANAGE EC, V14, P265, DOI [DOI 10.1080/014461996373511, 10.1080/014461996373511]
[5]  
CHENG Y, 1993, QSB PLUS QUANTITATIV
[6]   THE DISCRETE TIME-COST TRADEOFF PROBLEM REVISITED [J].
DE, P ;
DUNNE, EJ ;
GHOSH, JB ;
WELLS, CE .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1995, 81 (02) :225-238
[7]   RESOURCE LEVELING IN CONSTRUCTION BY OPTIMIZATION [J].
EASA, SM .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02) :302-316
[8]   RESOURCE-ALLOCATION VIA DYNAMIC-PROGRAMMING IN ACTIVITY NETWORKS [J].
ELMAGHRABY, SE .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1993, 64 (02) :199-215
[9]   Using genetic algorithms to solve construction time-cost trade-off problems [J].
Feng, CW ;
Liu, LA ;
Burns, SA .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) :184-189
[10]   RESOURCE-MANAGEMENT IN CONSTRUCTION [J].
KARAA, FA ;
NASR, AY .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03) :346-357