Finance-based scheduling of construction projects using integer programming

被引:74
作者
Elazouni, AM [1 ]
Gab-Allah, AA [1 ]
机构
[1] Zagazig Univ, Fac Engn, Construct Engn Dept, Zagazig, Egypt
来源
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE | 2004年 / 130卷 / 01期
关键词
scheduling; computer programming; construction industry;
D O I
10.1061/(ASCE)0733-9364(2004)130:1(15)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Construction scheduling is the process of devising schemes for sequencing activities. A realistic schedule fulfills the real concerns of users, thus minimizing the chances of schedule failure. The minimization of total project duration has been the concept underlying critical-path method/program evaluation and review technique (CPM/PERT) schedules. Subsequently, techniques including resource management and time-cost trade-off analysis were developed to customize CPM/PERT schedules in order to fulfill users' concerns regarding project resources, cost, and time. However, financing construction activities throughout the course of the project is another crucial concern that must be properly treated otherwise, nonrealistic schedules are to be anticipated. Unless contractors manage to procure adequate cash to keep construction work running according to schedule, the pace of work will definitely be relaxed. Therefore, always keeping scheduled activities in balance with available cash is a potential contribution to producing realistic schedules. This paper introduces an integer-programming finance-based scheduling method to produce financially feasible schedules that balance the financing requirements of activities at any period with the cash available during that same period. The proposed method offers twofold benefits of minimizing total project duration and fulfilling finance availability constraints.
引用
收藏
页码:15 / 24
页数:10
相关论文
共 17 条
[11]   Using machine learning and GA to solve time-cost trade-off problems [J].
Li, H ;
Cao, JN ;
Love, PED .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 1999, 125 (05) :347-353
[12]   Using improved genetic algorithms to facilitate time-cost optimization [J].
Li, H ;
Love, P .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 1997, 123 (03) :233-237
[13]   CONSTRUCTION TIME-COST TRADE-OFF ANALYSIS USING LP/IP HYBRID METHOD [J].
LIU, L ;
BURNS, SA ;
FENG, CW .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1995, 121 (04) :446-454
[14]  
Meyer WL, 1963, CIVIL ENG CONSTRUCTI, V2
[15]   HORIZON-VARYING, ZERO-ONE APPROACH TO PROJECT SCHEDULING [J].
PATTERSON, JH ;
HUBER, WD .
MANAGEMENT SCIENCE SERIES B-APPLICATION, 1974, 20 (06) :990-998
[16]   TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES [J].
REDA, R ;
CARR, RI .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (03) :475-486
[17]  
ROBINSON DR, 1975, MANAGE SCI, V22, P158, DOI 10.1287/mnsc.22.2.158