Robust and stable flexible job shop scheduling with random machine breakdowns using a hybrid genetic algorithm

被引:210
作者
Al-Hinai, Nasr [1 ]
ElMekkawy, T. Y. [1 ]
机构
[1] Univ Manitoba, Dept Mech & Mfg Engn, Winnipeg, MB R3T 5V6, Canada
关键词
Robust; Stable; Flexible job shop scheduling problem; Machine breakdowns; UNCERTAIN PROCESSING TIMES; PARTIAL ORDER SCHEDULES; SINGLE-MACHINE; EVOLUTIONARY ALGORITHMS; GENERATING ROBUST; SEARCH; DECOMPOSITION; OPTIMIZATION; HEURISTICS; FRAMEWORK;
D O I
10.1016/j.ijpe.2011.04.020
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper addresses the problem of finding robust and stable solutions for the flexible job shop scheduling problem with random machine breakdowns. A number of bi-objective measures combining the robustness and stability of the predicted schedule are defined and compared while using the same rescheduling method. Consequently, a two-stage Hybrid Genetic Algorithm (HGA) is proposed to generate the predictive schedule. The first stage optimizes the primary objective, minimizing makespan in this work, where all the data is considered to be deterministic with no expected disruptions. The second stage optimizes the bi-objective function and integrates machines assignments and operations sequencing with the expected machine breakdown in the decoding space. An experimental study and Analysis of Variance (ANOVA) is conducted to study the effect of different proposed measures on the performance of the obtained results. Results indicate that different measures have different significant effects on the relative performance of the proposed method. Furthermore, the effectiveness of the current proposed method is compared against three other methods; two are taken from literature and the third is a combination of the former two methods. (C) 2011 Elsevier B.V. All rights reserved.
引用
收藏
页码:279 / 291
页数:13
相关论文
共 66 条
[1]   An efficient hybridized genetic algorithm architecture for the flexible job shop scheduling problem [J].
Al-Hinai, Nasr ;
ElMekkawy, T. Y. .
FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2011, 23 (01) :64-85
[2]  
AlTurki UM, 1996, NAV RES LOG, V43, P573, DOI 10.1002/(SICI)1520-6750(199606)43:4<573::AID-NAV9>3.0.CO
[3]  
2-4
[4]   Robust scheduling of parallel. machines with sequence-dependent set-up costs [J].
Anglani, A ;
Grieco, A ;
Guerriero, E ;
Musmanno, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 161 (03) :704-720
[5]   Insertion techniques for static and dynamic resource-constrained project scheduling [J].
Artigues, C ;
Michelon, P ;
Reusser, S .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 149 (02) :249-267
[6]   Executing production schedules in the face of uncertainties: A review and some future directions [J].
Aytug, H ;
Lawley, MA ;
McKay, K ;
Mohan, S ;
Uzsoy, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 161 (01) :86-110
[7]   A priori parallel machines scheduling [J].
Bouyahia, Zied ;
Bellalouna, Monia ;
Jaillet, Patrick ;
Ghedira, Khaled .
COMPUTERS & INDUSTRIAL ENGINEERING, 2010, 58 (03) :488-500
[8]  
Brandimarte P., 1993, Annals of Operations Research, V41, P157, DOI 10.1007/BF02023073
[9]  
Branke J, 1998, LECT NOTES COMPUT SC, V1498, P119, DOI 10.1007/BFb0056855
[10]   Decomposition heuristics for robust job-shop scheduling [J].
Byeon, ES ;
Wu, SD ;
Storer, RH .
IEEE TRANSACTIONS ON ROBOTICS AND AUTOMATION, 1998, 14 (02) :303-313