Using detailed scheduling to obtain realistic operating policies for a batch processing facility

被引:33
作者
Bassett, MH [1 ]
Pekny, JF [1 ]
Reklaitis, GV [1 ]
机构
[1] PURDUE UNIV,SCH CHEM ENGN,W LAFAYETTE,IN 47907
关键词
D O I
10.1021/ie960470v
中图分类号
TQ [化学工业];
学科分类号
0817 ;
摘要
With many industries changing to a just-in-time manufacturing environment, the ability to reliably meet due dates and/or determine delivery/promise dates is gaining importance. In order to achieve this, the ability to determine operating policies based on realistic production plans is paramount. For these policies to be reasonable, the uncertain nature of the process must be addressed. These uncertainties include, but are not limited to, processing time fluctuations, equipment reliability/availability, process yields, demands, and manpower changes. In this paper we present a framework for addressing uncertainty by means of Monte Carlo sampling. This framework is not limited to a specific model, but results obtained show that the need of including sufficient detail is best satisfied by a scheduling model. A number of stopping criteria are derived, and the framework is utilized to obtain operating policies for two industrially-based examples.
引用
收藏
页码:1717 / 1726
页数:10
相关论文
共 19 条
[11]   ON THE JOB-SHOP SCHEDULING PROBLEM [J].
MANNE, AS .
OPERATIONS RESEARCH, 1960, 8 (02) :219-223
[12]   A REVIEW OF HIERARCHICAL PRODUCTION PLANNING AND ITS APPLICABILITY FOR MODERN MANUFACTURING [J].
MCKAY, KN ;
SAFAYENI, FR ;
BUZACOTT, JA .
PRODUCTION PLANNING & CONTROL, 1995, 6 (05) :384-394
[13]  
PANTELIDES CC, 1993, P 2 INT C FDN COMP A, P253
[14]  
PEKNY JF, 1993, P 2 INT C FDN COMP A, P275
[15]  
Pieruschka E., 1963, PRINCIPLES RELIABILI
[16]   REFORMULATION OF MULTIPERIOD MILP MODELS FOR PLANNING AND SCHEDULING OF CHEMICAL PROCESSES [J].
SAHINIDIS, NV ;
GROSSMANN, IE .
COMPUTERS & CHEMICAL ENGINEERING, 1991, 15 (04) :255-272
[17]   A GENERAL ALGORITHM FOR SHORT-TERM SCHEDULING OF BATCH-OPERATIONS .2. COMPUTATIONAL ISSUES [J].
SHAH, N ;
PANTELIDES, CC ;
SARGENT, RWH .
COMPUTERS & CHEMICAL ENGINEERING, 1993, 17 (02) :229-244
[18]   A COMPARATIVE-STUDY OF AGGREGATE PRODUCTION PLANNING STRATEGIES UNDER CONDITIONS OF UNCERTAINTY AND CYCLIC PRODUCT DEMANDS [J].
THOMPSON, SD ;
WATANABE, DT ;
DAVIS, WJ .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1993, 31 (08) :1957-1979
[19]  
Zentner M. G., 1994, Journal of Process Control, V4, P259, DOI 10.1016/0959-1524(94)80046-4