On-line control model for network construction projects

被引:2
作者
GolenkoGinzburg, D [1 ]
Gonik, A [1 ]
机构
[1] LUDAN ENGN CO LTD,TEL AVIV,ISRAEL
关键词
activity network; chance constraint; construction project; inspection point; on-line control;
D O I
10.1038/sj.jors.2600353
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
An activity-on-are network project of the PERT type with random activity durations is considered. For each activity, its accomplishment is measured in percentages of the total project. When operated, each activity utilizes resources of a pregiven capacity and no resource reallocation is undertaken in the course of the project's realization. Each activity can be operated at several possible speeds that are subject to random disturbances and correspond to one and the same resource capacity; that is, these speeds depend only on the degree of intensity of the project's realization. For example, in construction projects partial accomplishments are usually measured in percentages of the total project, while different speeds correspond to different hours a day per worker. The number of possible speeds is common to all activities. For each activity, speeds are sorted in ascending order of their average values-namely speeds are indexed. It is assumed that at any moment t > 0 activities, in operation at that moment, have to apply speeds of one and the same index that actually determines the project's speed. The progress of the project can be evaluated only via inspection at control points that have to be determined. The project's due date and the chance constraint to meet the deadline are pregiven. An on-line control model is suggested that, at each control point, faces a stochastic optimization problem. Two conflicting objectives are imbedded in the model: (1) to minimize the number of control points, and (2) to minimize the average index of the project's speeds which can be changed only at a control point. At each routine control point, decision-making centers on determining the next control point and the new index of the speeds (for all activities to be operated) up to that point. The model's performance is verified via simulation. The developed on-line control algorithm can be used for various PERT network projects which can be realized with different speeds, including construction projects and R&D projects.
引用
收藏
页码:175 / 183
页数:9
相关论文
共 18 条
[11]   A COMPARISON BETWEEN THE VERT PROGRAM AND OTHER METHODS OF PROJECT DURATION ESTIMATION [J].
KIDD, JB .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1987, 15 (02) :129-134
[12]   PLANNING AND CONTROL IN RESEARCH-AND-DEVELOPMENT [J].
PEARSON, AW .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1990, 18 (06) :573-581
[13]  
PRITSKER AAB, 1977, MODELING ANAL USING
[14]   WHY PROJECTS ARE ALWAYS LATE - A RATIONALE BASED ON MANUAL SIMULATION OF A PERT-CPM NETWORK [J].
SCHONBERGER, RJ .
INTERFACES, 1981, 11 (05) :66-70
[15]   ONLINE PRODUCTION CONTROL USING THE EVPI APPROACH [J].
SINUANYSTERN, Z ;
GOLENKOGINZBURG, D ;
KEREN, B .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1993, 67 (03) :344-357
[16]  
WALPOLE RE, 1978, PROBABILITY STATISTI
[17]   THE USE OF ADVANCED MANAGEMENT-TECHNIQUES IN RESEARCH-AND-DEVELOPMENT [J].
WATTS, KM ;
HIGGINS, JC .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1987, 15 (01) :21-29
[18]   PRACTICAL USE OF DISTRIBUTIONS IN NETWORK ANALYSIS [J].
WILLIAMS, TM .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1992, 43 (03) :265-270