IMPACTS OF DIFFERENT OBJECTIVE FUNCTIONS ON RESOURCE LEVELING IN CONSTRUCTION PROJECTS: A CASE STUDY

被引:36
作者
Damci, Atilla [1 ]
Polat, Gul [2 ]
机构
[1] Istanbul Tech Univ, Dept Civil Engn, TR-80626 Istanbul, Turkey
[2] Istanbul Tech Univ, Dept Civil Engn, Construct Management Grad Program, TR-80626 Istanbul, Turkey
关键词
scheduling; critical path method; resource levelling; genetic algorithm; GENETIC ALGORITHMS; OPTIMIZATION; SIMULATION; MODEL;
D O I
10.3846/13923730.2013.801909
中图分类号
TU [建筑科学];
学科分类号
081407 [建筑环境与能源工程];
摘要
A review of the recent literature on the models that focus on resource leveling in Critical Path Method networks shows that different objective functions have been used to optimize resource utilization. The main objective of this study is to investigate the impacts of using different objective functions on resource utilization histograms in Critical Path Method networks. For this purpose, nine different resource leveling objective functions were optimized via a genetic algorithm-based model. The model was developed using actual data obtained from a steel framed industrial building construction project. It was found that each of these objective functions generates different resource utilization histograms. In order to determine the improvement levels achieved by resource leveling using nine different objective functions, the improvement percentage in each parameter and the average improvement percentage for each objective function were calculated. Even though the objective function that involves the minimization of the sum of the square of the deviations in daily resource usage provided the best average improvement percentage in the studied case, another objective function(s) may provide better average improvement percentage in different projects. The contractor should consider all objective functions for resource leveling and select the one(s) that provides the best average improvement percentage.
引用
收藏
页码:537 / 547
页数:11
相关论文
共 44 条
[1]
Ahuja H.N., 1976, Construction Performance Control by Networks
[2]
Al-Tabtabai H., 1999, ENG CONSTR ARCHIT MA, V6, P121, DOI [10.1108/eb021105, DOI 10.1108/EB021105]
[3]
[Anonymous], 2010, EV 2010
[4]
Burgess A.R., 1962, J IND ENGINEERING, V13, P76
[5]
A two-phase GA model for resource-constrained project scheduling [J].
Chen, Po-Han ;
Weng, Haijie .
AUTOMATION IN CONSTRUCTION, 2009, 18 (04) :485-498
[6]
Entropy-based scheduling of resource-constrained construction projects [J].
Christodoulou, Symeon ;
Ellinas, Georgios ;
Aslani, Pooyan .
AUTOMATION IN CONSTRUCTION, 2009, 18 (07) :919-928
[7]
Efficient Hybrid Genetic Algorithm for Resource Leveling via Activity Splitting [J].
Doulabi, Seyed Hossein Hashemi ;
Seifi, Abbas ;
Shariat, Seyed Yasser .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (02) :137-146
[8]
Dubey A, 1993, THESIS U BRIT COLUMB
[9]
RESOURCE LEVELING IN CONSTRUCTION BY OPTIMIZATION [J].
EASA, SM .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02) :302-316
[10]
Optimizing Resource Leveling in Construction Projects [J].
El-Rayes, Khaled ;
Jun, Dho Heon .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2009, 135 (11) :1172-1180