A multi-objective tabu search for a single-machine scheduling problem with sequence-dependent setup times

被引:37
作者
Choobineh, F. Fred [1 ]
Mohebbi, Esmail [1 ]
Khoo, Hansen [1 ]
机构
[1] Univ Nebraska, Dept Ind & Management Syst Engn, Lincoln, NE 68588 USA
关键词
scheduling; sequence-dependent setup; multi-objective; tabu search;
D O I
10.1016/j.ejor.2005.04.038
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
An m-objective tabu search algorithm for sequencing of n jobs on a single machine with sequence-dependent setup times is proposed. The algorithm produces a solution set that is reflective of the objectives' weights and close to the best observed values of the objectives. We also formulate a mixed integer linear program to obtain the optimal solution of a three-objective problem. Numerical examples are used to study the behavior of the proposed m-objective tabu search algorithm and compare its solutions with those of the mixed integer linear program. (c) 2005 Elsevier B.V. All rights reserved.
引用
收藏
页码:318 / 337
页数:20
相关论文
共 42 条
[1]   SOLVING THE MULTIPLE-MACHINE WEIGHTED FLOW TIME PROBLEM USING TABU SEARCH [J].
BARNES, JW ;
LAGUNA, M .
IIE TRANSACTIONS, 1993, 25 (02) :121-128
[2]   SCHEDULING JOBS WITH LINEAR DELAY PENALTIES AND SEQUENCE DEPENDENT SETUP COSTS [J].
BARNES, JW ;
VANSTON, LK .
OPERATIONS RESEARCH, 1981, 29 (01) :146-160
[3]   SINGLE-MACHINE SCHEDULING TO MINIMIZE WEIGHTED EARLINESS SUBJECT TO NO TARDY JOBS [J].
CHAND, S ;
SCHNEEBERGER, H .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1988, 34 (02) :221-230
[4]   A NOTE ON THE SINGLE-MACHINE SCHEDULING PROBLEM WITH MINIMUM WEIGHTED COMPLETION-TIME AND MAXIMUM ALLOWABLE TARDINESS [J].
CHAND, S ;
SCHNEEBERGER, H .
NAVAL RESEARCH LOGISTICS, 1986, 33 (03) :551-557
[5]   SCHEDULING A SINGLE-MACHINE TO MINIMIZE 2 CRITERIA - MAXIMUM TARDINESS AND NUMBER OF TARDY JOBS [J].
CHEN, CL ;
BULFIN, RL .
IIE TRANSACTIONS, 1994, 26 (05) :76-84
[6]  
Cheng TCE, 2000, PROD OPER MANAG, V9, P262, DOI 10.1111/j.1937-5956.2000.tb00137.x
[7]   A local search algorithm for jobshop scheduling problems with alternative operations and sequence-dependent setups [J].
Choi, IC ;
Choi, DS .
COMPUTERS & INDUSTRIAL ENGINEERING, 2002, 42 (01) :43-58
[8]  
Czyzzak P., 1998, Journal of Multi-Criteria Decision Analysis, V7, P34, DOI [DOI 10.1002/(SICI)1099-1360(199801)7:13.0.CO
[9]  
2-6, DOI 10.1002/(SICI)1099-1360(199801)7:1<34::AID-MCDA161>3.0.CO
[10]  
2-6, 10.1002/(SICI)1099-1360(199801)7:13.0.CO